Feature · Sundargarh, Odisha

Mahanadi Mines Plans a 5.26-Million-Tonne-a-Year Coal Mine in Sundargarh, Odisha

Mahanadi Mines and Minerals Private Limited has received environmental clearance for a ₹2,600-crore, 5.26-million-tonne-a-year opencast coal mine in Hemgir, Odisha.

Where it stands: Bijahan Coal Block — “Forest land use approved” since 28 Oct 2026. 4 related filings are listed below. Status data as of 27 Nov 2026, 6:36 am IST.

Mahanadi Mines and Minerals Private Limited proposes to build the Bijahan Coal Block, a greenfield opencast coal mine with a production capacity of 5.26 million metric tonnes per annum (MMTPA). The project is located across the villages of Bijahan, Bhograkachhar, Girisuan, and Jharpalam in Hemgir tehsil of Sundargarh district, Odisha. According to the applicant's executive summary, the project will cost ₹2,600 crore. The project has been granted environmental approval and its forest land use is approved.

ItemDetail
Capacity5.26 MMTPA
Project cost₹2,600 crore
Total land1,100 hectares (2,718 acres)
Forest land608.64 hectares (1,504 acres)
Direct jobs1,270

What is planned

The applicant proposes to extract coal using a mechanized opencast method employing a shovel-dumper combination. According to the executive summary, the mine will have a peak production capacity of 5.26 MMTPA and an estimated life of 32.5 years. The project also envisages the installation of a Coal Handling Plant (CHP). The total mineable reserve is estimated at 161.20 million tonnes.

Where it is and the land

The project requires a total mine lease area of 1,100 hectares (2,718 acres). According to the project description, this includes 313.89 hectares (775 acres) of private tenancy land, 177.47 hectares (438 acres) of government land, and 608.64 hectares (1,504 acres) of forest land.

The lease area covers land across four villages. The applicant states that the villages of Bijahan and Bhograkachhar are located within the leasehold area and will be displaced, affecting an estimated 434 families. The villages of Girisuan and Jharpalam are located outside the leasehold area but will be affected by the project.

Cost, jobs and schedule

The total cost of the project is estimated at ₹2,600 crore. The applicant's documents state that the project will generate direct employment for about 1,270 persons, while more than 3,000 people are expected to benefit indirectly through transportation, trading, and contract works.

Water, power and connectivity

The project will require 1,600 kilolitres per day (KLD) of water, comprising 70 KLD for domestic use and 1,530 KLD for industrial requirements. This will be sourced from groundwater borewells and treated mine sump water. Power requirements for the peak production will be met by installing two 5 MVA 33/3.3 kV outdoor transformers at a proposed substation.

For coal evacuation, the applicant plans to transport overburden and coal using 85-tonne and 35-tonne trucks. Initially, coal will be transported by road to nearby power plants and railway sidings. The applicant notes that once the proposed Sardega–Bhalumunda railway line is completed by Indian Railways, the entire 5.26 MMTPA of coal will be transported by rail.

Environmental concerns and safeguards

The opencast mining operations will involve drilling, blasting, and overburden removal, which are anticipated to increase particulate matter and noise levels. To mitigate these impacts, the applicant proposes controlled blasting, wet drilling, and regular water sprinkling on haul roads using 26-kilolitre water sprinklers.

Out of the 631.54 hectares (1,560 acres) of excavated quarry area, 495.54 hectares (1,224 acres) will be backfilled and reclaimed with plantation. A final mine void of 136 hectares (336 acres) with a depth of 150 meters will be converted into a water body. The applicant also plans to develop a greenbelt over 14.8 hectares (36 acres) and plant a total of 15,20,500 trees over the life of the mine.

What was said at the public hearing

A public hearing was held on December 1, 2023, at Village Bijahan, presided over by the Additional District Magistrate of Sundargarh. According to the minutes, 400 to 450 people attended.

Local residents raised concerns about land acquisition, demanding that compensation for land, structures, and trees be provided strictly under the 2013 land acquisition act. Villagers also demanded direct employment for local youths, the establishment of a proper rehabilitation and resettlement (R&R) colony, and the issuance of forest rights titles (patta) before displacement. Environmental concerns were also raised, with residents demanding strict measures to control air and water pollution, as well as the protection of nearby historical sites and forests from blasting impacts. The applicant committed to following the 2013 act for compensation, providing skill development training, and implementing pollution control measures.

Approvals so far

The project has been granted environmental approval and its forest land use has been approved.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Bijahan Coal Block
New project · Jharpalanka, Hemgir, Sundargarh
Forest land useForest land use approved16 Jan 202528 Oct 2026
Bijahan Coal Block
New project · Latapani, Hemgir, Sundargarh
Environmental approvalEnvironmental approval granted21 Feb 202523 Feb 2026
Bijahan Coal Block
New project · Forest, Hemgir, Sundargarh
Forest land useNot approved11 Apr 202626 May 2026
Bijahan Coal Block
New project · Jharpalanka, Hemgir, Sundargarh
Forest land useForest land use approved11 Jun 202624 Jun 2026

Statuses update automatically twice a day.

About this page

Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.