Central Coalfields Limited (CCL) plans to build the Chandragupt Opencast Coal Mine Project in the Keredari and Tandwa sub-districts of Hazaribagh and Chatra districts, Jharkhand. The project will have a peak capacity of 20 million tonnes per annum (MTPA) and a nominal capacity of 15 MTPA. It will cover 1,495 hectares and cost an estimated ₹973.5 crore. The project has been granted environmental approval.
| Item | Detail |
|---|---|
| Applicant | Central Coalfields Limited |
| Location | Hazaribagh and Chatra districts, Jharkhand |
| Capacity | 15 MTPA (nominal), 20 MTPA (peak) |
| Project Area | 1,495 hectares |
| Estimated Cost | ₹973.5 crore |
| Estimated Life | 41 years |
What is planned
The Chandragupt Opencast Coal Mine Project is a greenfield project in the North Karanpura Coalfield. According to the pre-feasibility report, the mine will be worked by the opencast method using a combination of surface miners and shovel-dumpers. The project is designed to extract an estimated 465.59 million tonnes of mineable coal reserves over a life of 41 years.
The project will involve the excavation of 1,300.40 hectares for the quarry. Coal will be transported from the mine to a pit-head coal handling plant (CHP) by dumpers, and then to the Amrapali railway siding by a closed conveyor system.
Where it is and the land
The project is located in the Hazaribagh and Chatra districts of Jharkhand, covering nine revenue villages: Badhaikhap, Bukru, Chatti-Bariyatu, Jordag, Nawakhap, Pachra/Pachanda, Peto, Sijhua, and Ursu. The total project area of 1,495 hectares includes 699.38 hectares of forest land and 795.62 hectares of non-forest land.
The land use plan allocates 1,300.40 hectares for the quarry, 109.55 hectares for a greenbelt, 18.58 hectares for roads, 16.43 hectares for embankments, 13.36 hectares for water bodies, 12.70 hectares for a solar power plant, 11.56 hectares for infrastructure, 7.86 hectares for the CHP, 2.90 hectares for a safety zone, and 1.66 hectares for a stream diversion.
Cost, jobs and schedule
The estimated capital investment for the project is ₹973.5 crore. The project is expected to generate 1,247 direct jobs. The mine is planned to reach its rated capacity of 15 MTPA by the sixth year of operation.
Water, power and connectivity
The peak industrial water demand is projected at 6,015 kilolitres per day (KLD), and domestic water demand at 745 KLD, totaling 6,760 KLD. Water will be sourced primarily from mine seepage.
Power will be supplied from the upcoming Tandwa Substation of the Damodar Valley Corporation (DVC) via a 33 kV double-circuit feeder. A 8 MW solar power plant is also proposed to cater to the project's energy needs.
The site is accessible via State Highway 7, which connects Tandwa with Hazaribagh. The nearest railway station is Ray Station, about 37 kilometres away.
Environmental concerns and safeguards
The project involves the diversion of the Chotki stream, which flows through the mine boundary. The Barki River, which flows along the western boundary, will not be diverted.
The project will generate an estimated 965.53 million cubic metres of overburden (including re-handling). Initially, overburden will be stored on the coal-bearing area for the first six years and then re-handled back into the mine void.
The EIA report notes the presence of 21 Schedule-I fauna species in the study area, and a wildlife management plan has been prepared with a budget of ₹5,360.96 lakh.
What was said at the public hearing
Public hearings were held in Chatra and Hazaribagh districts in February 2023. Villagers raised concerns about compensation, employment, resettlement, and the provision of basic facilities like electricity, water, roads, and healthcare. They also expressed concerns about environmental pollution and the verification of land ownership documents.
CCL representatives assured the villagers that compensation and resettlement would be carried out according to company policies and government regulations. They also promised to provide basic amenities and support for schools and medical facilities.
Approvals so far
The project was granted environmental approval on October 10, 2026. An application for Stage-I forest clearance was submitted in April 2021.
Filings for this project
| Filing | Approval sought | Status | Filed | Status since |
|---|---|---|---|---|
| Chandragupt Opencast Coal Mine Project New project · Bhadaikhap, Keredari, Hazaribagh | Environmental approval | Returned to applicant | 31 Jul 2023 | 15 Mar 2024 |
| Chandragupt Opencast Coal Mine Project New project · Bhadaikhap, Keredari, Hazaribagh | Environmental approval | Environmental approval granted | 6 Nov 2024 | 2 Jan 2025 |
| Chandragupt Opencast Coal Mine Project Amendment · Bhadaikhap, Keredari, Hazaribagh | Environmental approval | Environmental approval granted | 25 Aug 2026 | 10 Oct 2026 |
Statuses update automatically twice a day.
About this page
Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.