UPEIDA Plans a 15-Kilometre Chitrakoot Link Expressway in Uttar Pradesh

The Uttar Pradesh Expressways Industrial Development Authority proposes a four-lane greenfield expressway in Chitrakoot, costing ₹939 crore.

Where it stands: Environment Clearance for Development of Access Controlled Greenfield 4 Lane (Expandable… — “Under environmental review” since 12 Nov 2026. Status data as of 27 Nov 2026, 6:36 am IST.

The Uttar Pradesh Expressways Industrial Development Authority (UPEIDA) proposes to build the Chitrakoot Link Expressway, an access-controlled greenfield four-lane highway that will be expandable to six lanes. The project will be located in Ranipur Khaki village, Karwi sub-district, Chitrakoot district, Uttar Pradesh. It will span 15.172 kilometres and require 639.18 hectares (1,579.4 acres) of land. The estimated cost is ₹939.67 crore. The application for environmental clearance is currently cleared for an impact study.

ItemDetail
ApplicantUttar Pradesh Expressways Industrial Development Authority (UPEIDA)
LocationKarwi, Chitrakoot, Uttar Pradesh
Length15.172 kilometres
Land required639.18 hectares (1,579.4 acres)
Estimated cost₹939.67 crore

What is planned

The expressway will connect the Bundelkhand Expressway near Gonda village to NH 135 BG near Ahmad Ganj village. According to the alternative alignment analysis filed with the application, the road will have a proposed right-of-way of 110 metres. The design speed is 120 kilometres per hour, except at the interchange, which will be designed for 60 kilometres per hour. The project includes one interchange, one major bridge, four minor bridges, 25 culverts, and three transmission line crossings.

Where it is and the land

The alignment passes near several water bodies and roads, including the Karwi Road, NH-76, Akbara Tal, Durga Das Talab, Parari Nala, Barwa Nala, Ghaira Nala, and Thothi Nala. The layout plan notes that the Bharatpur Pahar Protected Forest is in the vicinity. The layout plan states that there are no national parks, wildlife sanctuaries, biosphere reserves, or wildlife corridors within 10 kilometres of the project site.

According to the documents, multiple alignment options were evaluated. Following a site visit on 28 February 2024, UPEIDA officials approved "Option 6". This alignment was selected to avoid major impacts on habituated areas and operational stone crushers, which would have caused revenue losses and required significant resettlement. While other options would have affected up to 217 houses, the chosen alignment will affect approximately 17 temporary structures and partially affect one petrol pump. However, this option requires hill cutting for about 750 metres, with an average cutting height of 50 metres on both sides.

Environmental concerns and safeguards

Baseline environmental data was collected between December 2025 and February 2026. Air quality monitoring at locations including Gonda Ka Purwa, Bharatkoop, Gopalpur, and Ahmad Ganj showed PM10 levels varying from 78 to 84 micrograms per cubic metre, and PM2.5 levels from 39 to 42 micrograms per cubic metre. Noise levels during the day ranged from 49.7 to 51.3 dB(A), and night levels were between 35.1 and 35.8 dB(A).

Soil in the study area is predominantly sandy loam, with organic carbon varying from 0.92 percent to 1.06 percent. Surface water testing at Akbara Tal, Barwa Nala, and a pond near Ahmad Ganj showed pH levels between 7.36 and 8.14. Groundwater parameters were reported to be within permissible limits for drinking water, with total dissolved solids ranging from 282 to 349 milligrammes per litre.

Approvals so far

The project's application for environmental clearance was filed on 14 June 2026. As of 28 October 2026, the proposal has been cleared for an environmental impact study.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Environment Clearance for Development of Access Controlled Greenfield 4 Lane…
Early planning · Ahmad Ganj, Karwi, Chitrakoot
Environmental approvalUnder environmental review14 Jun 202612 Nov 2026

Statuses update automatically twice a day.

About this page

Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.