Feature · Shrivardhan, Raigarh, Maharashtra

MMB Dighi Marine Shipyard Cluster: Shipbuilding and Repair Hub in Raigad, Maharashtra

The Maharashtra Maritime Board proposes a major shipbuilding and repair cluster on 738.59 hectares in Dighi, Raigad, involving an estimated investment of ₹27,675 crore.

Where it stands: Application for Terms of Reference (ToR) for Development of Marine Shipyard Cluster… — “Under environmental review” since 17 Nov 2026. Status data as of 27 Nov 2026, 6:36 am IST.

The Maharashtra Maritime Board (MMB) proposes to develop a greenfield Marine Shipyard Cluster (MSC) at Creek village in the Shrivardhan sub-district of Raigarh district, Maharashtra. The project aims to establish a large-scale shipbuilding and ship repair hub on 738.59 hectares of land. According to the application, the project is estimated to cost ₹27,675 crore, though an earlier pre-feasibility report estimated the capital expenditure at ₹33,766 crore. The project filed an application for Terms of Reference (ToR) on 16 October 2026 and is currently under environmental review.

ItemDetail
ApplicantMaharashtra Maritime Board
LocationCreek village, Shrivardhan, Raigarh, Maharashtra
Total Area738.59 hectares
Estimated Cost₹27,675 crore
Current StatusUnder environmental review

What is planned

According to the techno-economic feasibility report filed with the application, the Marine Shipyard Cluster will focus on large-scale shipbuilding and ship repair facilities. The cluster is designed to target an annual shipbuilding output of approximately 1.35 million gross tonnes (GT), equivalent to around eight Very Large Crude Carrier (VLCC) sized vessels per annum.

The proposed infrastructure includes two VLCC-sized dry docks, each approximately 500 metres long, capable of semi-tandem shipbuilding. For ship repair, the facility will feature two additional VLCC-sized dry docks, a shiplift system, and multiple dry berths to handle both large commercial vessels and smaller ships. The project scope explicitly excludes ship recycling to maintain policy alignment and manage regulatory complexity.

Where it is and the land

The project is located on the south bank of Rajpuri Creek, adjacent to the villages of Dighi and Kudgaon. The application states the project requires 738.59 hectares (1,825 acres) of land.

The pre-feasibility report notes that the existing land area is irregularly shaped and lacks sufficient waterfront. To mitigate this, the primary shipyard land area is proposed to be located in the nearshore zone, requiring significant land reclamation. The report estimates that achieving the required layout will involve reclaiming land in the inter-tidal zone and acquiring additional land for secondary and ancillary uses.

Cost, jobs and schedule

The most recent filing places the project cost at ₹27,675 crore. However, the June 2026 pre-feasibility report provided a preliminary capital expenditure estimate of ₹33,766 crore, which included ₹7,118 crore for dredging, ₹1,867 crore for reclamation, and ₹9,786 crore for dry docks.

Water, power and connectivity

The site is located adjacent to Dighi Port. Road connectivity currently relies on state roads, but future plans include widening the existing road network and developing a 20-kilometre four-lane road connecting Dighi to the Agardanda terminal. A dedicated 35-kilometre rail corridor from Agardanda to Roha is also proposed under the Comprehensive Port Connectivity Plan.

Environmental concerns and safeguards

The pre-feasibility report identifies that the site's waterfront falls under a Coastal Regulation Zone (CRZ-I) categorisation, which designates highly sensitive coastal areas where development is heavily restricted.

Developing the site will require extensive dredging and reclamation. The report estimates that approximately 72 million cubic metres of material will need to be dredged to create the necessary water depths of -14 metres Chart Datum (CD) for the shipyard and a 15-kilometre access channel. Sub-bottom profiling surveys indicate the presence of cohesive sediments overlying basement rock, which will require specific foundation and ground improvement strategies, such as piling and grouting, to support heavy shipyard structures.

Approvals so far

The Maharashtra Maritime Board filed the application for Terms of Reference (ToR) on 16 October 2026. The proposal is currently under environmental review.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Application for Terms of Reference (ToR) for Development of Marine Shipyard…
Early planning · Creek, Shrivardhan, Raigarh
Environmental approvalUnder environmental review16 Oct 202617 Nov 2026