Dighi Port Expansion: 140 MMTPA Multi-Cargo Port in Raigad, Maharashtra

Dighi Port Limited is proposing a ₹44,060 crore expansion of its port facilities on the Rajpuri Creek in Raigad, Maharashtra, to handle 140 million metric tonnes of cargo per year.

Where it stands: Master Plan for Expansion of Dighi Port, by Dighi Port Limited at Taluka Shrivardhan and… — “More information requested” since 17 Nov 2026. 2 related filings are listed below. Status data as of 27 Nov 2026, 6:36 am IST.

Dighi Port Limited is proposing a major expansion of the Dighi Port, located on the banks of the Rajpuri Creek in the Shrivardhan and Murud talukas of Raigad district, Maharashtra. The project aims to increase the port's cargo handling capacity to 140 MMTPA (million metric tonnes per annum) by adding 5,375 metres of new quay length. According to the project filings, the expansion is estimated to cost ₹44,060 crore. The proposal is currently under environmental and coastal review.

ItemDetail
ApplicantDighi Port Limited
LocationShrivardhan and Murud talukas, Raigad, Maharashtra
Total capacity140 MMTPA
Total land area584.5 hectares (1,444.3 acres)
Estimated cost₹44,060 crore

What is planned

According to the pre-feasibility report, the master plan involves expanding the port into a multi-cargo hub handling dry bulk, containers, liquid cargo, and cryogenic gases like LNG and LPG. The applicant proposes to build new multipurpose berths on both the northern (Agardanda) and southern (Dighi) sides of the creek, bringing the total quay length to 7,000 metres. The plans also include two Single Point Mooring (SPM) stations, a 650-metre turning circle, and a navigational channel dredged to a depth of 17.8 metres.

To protect the harbour, the applicant plans to construct 4,600 metres of breakwaters (1,400 metres on the south and 3,200 metres on the north). The environmental impact assessment (EIA) report states that 114 million cubic metres of material will be dredged, updating an earlier pre-feasibility report estimate of 60 million cubic metres.

Where it is and the land

The project is situated on the Rajpuri Creek, with facilities split between Dighi village on the southern bank and Agardanda village on the northern bank. The total project area is 584.5 hectares (1,444.3 acres). According to the pre-feasibility report, this includes 141 hectares (348.4 acres) of already reclaimed land, 139.5 hectares (344.7 acres) of existing land, and 304 hectares (751.2 acres) of new land to be reclaimed from the intertidal zone.

Cost, jobs and schedule

The project filings estimate the cost of the expansion at ₹44,060 crore, though the EIA report mentions a figure of ₹42,490 crore. According to the EIA report, the expansion will generate employment for 500 workers during the construction phase. Once operational, the expanded port is expected to create 500 direct jobs and 2,000 indirect jobs.

Water, power and connectivity

The expanded port will require 51.4 MLD (million litres per day) of water. The applicant proposes to meet the 50 MLD expansion requirement by building a seawater desalination plant in phases. Power requirements will increase to 940 MWh per day, which will be sourced from the Maharashtra State Electricity Distribution Company Limited.

For connectivity, the pre-feasibility report outlines plans for a two-lane concrete road connecting to National Highway 66. The applicant also proposes to develop a new railway line connecting the northern side of the port at Agardanda to the Roha railway station, approximately 36 kilometres away.

Environmental concerns and safeguards

The project site is located 4.35 kilometres from the Phansad Wildlife Sanctuary, and a turtle nesting site is 3.3 kilometres away. The EIA report notes that dredging and reclamation could increase suspended sediments and affect marine habitats. To mitigate dust from dry bulk cargo, the applicant plans to install a dust suppression system with sprinklers at conveyor transfer points and stockyards. Sewage and effluent treatment plants will be built to handle wastewater, and the brine reject from the desalination plant will be discharged into the sea through a marine outfall.

What was said at the public hearing

A public hearing was held on 17 August 2026. Local residents and fishermen raised concerns that dredging and the new breakwaters would destroy fish breeding grounds and disrupt the high and low tide cycles. Attendees also expressed fears that the expansion would restrict fishing routes, cause flooding in adjacent lands, and potentially damage the nearby Murud-Janjira fort.

In response, the applicant stated that dredging would be done using cutter suction dredgers without explosives, and that fishing boats would not be restricted from navigating the Rajpuri Creek. The applicant also committed ₹4.56 crore to an environmental management plan, which includes funds for technical training, upgrading a local jetty, and building a fish market and dispensary for the fishing community.

Approvals so far

The project is currently under environmental and coastal review. The Ministry of Environment, Forest and Climate Change granted the Terms of Reference for the expansion on 7 November 2022. On 6 August 2025, the Maharashtra Coastal Zone Management Authority recommended the balance work of the project for coastal regulation zone clearance.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Master Plan for Expansion of Dighi Port, by Dighi Port Limited at Taluka…
Expansion · Na, Murud, Raigarh
Coastal reviewMore information requested23 Oct 202617 Nov 2026
Master Plan for Expansion of Dighi Port, by Dighi Port Limited at Taluka…
Expansion · Na, Murud, Raigarh
Environmental approvalMore information requested24 Oct 20265 Nov 2026

Statuses update automatically twice a day.

About this page

Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.