ERCPCL Plans an 875-Crore Barrage on the Mej River in Bundi, Rajasthan

Eastern Rajasthan Canal Project Corporation plans a barrage across the Mej River in Bundi, Rajasthan, to supply drinking water to 21 districts, requiring 11,683 hectares and ₹874.9 crore.

Where it stands: Diversion of Forest Land for the Construction of Mej Barrage Across Mej River — “Under forest review” since 28 Oct 2026. 2 related filings are listed below. Status data as of 27 Nov 2026, 6:36 am IST.

Eastern Rajasthan Canal Project Corporation (ERCPCL) plans to construct the Mej Barrage across the Mej River near the villages of Dapta and Kharyata in Indragarh tehsil, Bundi district, Rajasthan. The project is designed to act as a balancing reservoir to supply drinking water to water-deficit areas. It will require a total of 11,683.15 hectares (28,869.6 acres) of land and is estimated to cost ₹874.9 crore. Applications for the project are currently under forest and wildlife review.

ItemDetail
ApplicantEastern Rajasthan Canal Project Corporation
LocationIndragarh, Bundi, Rajasthan
Total Land11,683.15 hectares
Forest Land519.866 hectares
Project Cost₹874.9 crore
Gross Capacity102.16 MCM

What is planned

According to the pre-feasibility report filed with the application, the Mej Barrage is an important part of the Modified Parbati-Kalisindh-Chambal (MPKC) Link Project. The broader initiative aims to transfer surplus water available during the monsoon season from the Kunnu, Kul, Parwati, Kalisindh, and Mej river sub-basins to the Banas, Morel, Banganga, Kalisil, Gambhir, and Parbati river sub-basins.

The report says the Mej Barrage will serve as a balancing reservoir. Water from the barrage will be diverted to Bisalpur and Isarda via Galwa, and onward to Doongri for further utilization. The project intends to provide safe drinking water to a targeted population across 21 districts of Eastern Rajasthan and will also help recharge groundwater.

The applicant proposes a composite dam featuring both concrete overflow and non-overflow sections, alongside an earthen embankment. The gross capacity of the barrage is planned at 102.16 MCM (million cubic meters), with a net water balance of 201.70 MCM at the location.

Technical specifications in the report detail that the earthen embankment will be 2,647 meters long, with a 5.5-meter wide black-topped road proposed on top. The concrete overflow section will be 140 meters long, equipped with eight radial crest gates measuring 14 meters by 13 meters. The Full Reservoir Level (FRL) and Maximum Water Level (MWL) are set at RL 215.0 meters, while the Top Bank Level will be RL 219.0 meters. The design flood for the barrage is 8,550 cumecs.

The project will also involve the construction of a coffer dam, river protection works using wire crates filled with stones, and a SCADA system for the automation of the barrage. Additionally, the applicant plans to build 840 square meters of infrastructure, including office and non-residential buildings.

Where it is and the land

The barrage site is situated near Kharyata and Dapta villages in Indragarh tehsil of Bundi district. According to the pre-feasibility report, the location is 65 kilometers away from Bundi district via the Lakheri road, accessible by a bitumen road and a kacha track. The geographical coordinates are 25°36'34" N latitude and 76°10'50" E longitude.

The Mej River is a left-bank tributary of the Chambal River. It originates east of Mandalgarh tehsil in Bhilwara district and joins the Chambal near Bhaius Khana village in Kota district. The total catchment area for the Mej barrage extends over 5,830 square kilometers across Bhilwara, Bundi, and Tonk districts.

Filings indicate the project requires a total of 11,683.15 hectares (28,869.6 acres) of land. This includes 519.866 hectares (1,284.6 acres) of forest land that must be diverted for the construction. Land records submitted with the application list various parcels of government, forest, and barren land across multiple villages in the region.

Cost, jobs and schedule

The latest filings state the project cost is ₹874.9 crore. The pre-feasibility report notes that the construction of the Mej Barrage was prioritized in the 2024-25 budget speech to address drinking water needs, with an allocated figure of ₹875 crore. An earlier technical estimate mentioned in the report had framed the cost at ₹324.35 crore, but the most recent filings confirm the ₹874.9 crore figure. The documents do not specify the expected construction schedule or the number of jobs the project will create.

Approvals so far

The project requires multiple clearances to proceed. The application for the diversion of forest land was filed on October 8, 2026, and has been under forest review since October 28, 2026. A separate application for wildlife clearance was filed on January 27, 2026, and remains under wildlife review.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Diversion of Forest Land for the Construction of Mej Barrage Across Mej River
New project · Karwala Ki Jhonparyan, Keshoraipatan, Bundi
Wildlife reviewUnder wildlife review27 Jan 202627 Jan 2026
Diversion of Forest Land for the Construction of Mej Barrage Across Mej River
New project · Dapta, Indragarh, Bundi
Forest land useUnder forest review8 Oct 202628 Oct 2026

Statuses update automatically twice a day.

About this page

Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.