Indore-Budni Broad Gauge Rail Line: A ₹7,474-Crore Project

Rail Vikas Nigam Ltd is developing a new broad gauge rail line in Dewas, Madhya Pradesh, a ₹7,474-crore project that has received forest land use approval.

Where it stands: Indore-Budni New Bg Rail Line Project — “Forest land use approved” since 14 Nov 2026. Status data as of 27 Nov 2026, 6:36 am IST.

Rail Vikas Nigam Ltd is developing the Indore-Budni new broad gauge rail line project in Madhya Pradesh. The project is located in Adanya village in the Kannod sub-district of Dewas district. Estimated to cost ₹7,474 crore, the new railway line requires a total of 12.77 hectares (31.5 acres) of land. As of November 2026, the project has received approval for forest land use.

ItemDetail
ApplicantRail Vikas Nigam Ltd
Project TypeNew broad gauge rail line
LocationAdanya, Kannod, Dewas, Madhya Pradesh
Total Land12.77 hectares (31.5 acres)
Forest Land6.44 hectares (15.9 acres)
Estimated Cost₹7,474 crore
Current StatusForest land use approved

Where it is and the land

The new broad gauge railway line will pass through Adanya village, located in the Kannod sub-district of Dewas district in Madhya Pradesh. The project requires a total land area of 12.77 hectares (31.5 acres). Of this total requirement, 6.44 hectares (15.9 acres) is designated as forest land.

Approvals so far

The project requires forest clearance for the diversion of forest land. The application for forest clearance was filed on 12 July 2025. According to the project's tracking records, the forest land use was officially approved on 14 November 2026.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Indore-Budni New Bg Rail Line Project
New project · Adanya, Kannod, Dewas
Forest land useForest land use approved12 Jul 202514 Nov 2026