Oil and Natural Gas Corporation Limited (ONGC) proposes to drill 78 development wells for the onshore production of oil and gas in Bharuch district, Gujarat. The wells will be spread across 12 Petroleum Mining Leases (PMLs) and one Petroleum Exploration Licence (PEL) block, covering the Ankleshwar, Motwan, Gandhar, Kim, Jambusar, West Matar and West Amod fields. The project aims to produce 1,246 metric tonnes per day of crude oil. The estimated cost of drilling the 78 wells is ₹1,598.05 crore. The proposal is currently under environmental review.
What is planned
According to the pre-feasibility report filed with the application, ONGC plans to drill 68 wells within 12 PMLs and 10 wells in the OALP Block CB-ONHP-2021/2 (West Amod Field), which is presently under a PEL. The lease areas cover a total of 579.90 square kilometres.
| Item | Detail |
|---|---|
| Total wells | 78 |
| Envisaged production | 1,246 MT/day of crude oil |
| Drilling depth | 1,300 to 3,300 metres |
| Drilling duration | 30 to 60 days per well |
| Total project cost | ₹1,598.05 crore |
Drilling operations will be carried out round-the-clock using electrical and new-generation rigs. Once drilling is completed, if sufficient indications of hydrocarbons are noticed, the well will be tested and completed for production. The crude oil will be transported through pipelines to the nearest Gas Gathering Station (GGS) or Early Production System (EPS).
If economic quantities of hydrocarbons are not found, the well will be permanently abandoned, sealed with cement plugs, and the site will be restored.
Where it is and the land
The 78 well sites are located in the Ankleshwar, Hansot, Vagra, Jambusar and Amod talukas of Bharuch district.
The project requires 150 hectares of non-forest land in total. During drilling, each well will require a land area of 130 metres by 130 metres. The land is privately owned agricultural and other land, which will be taken on a temporary lease or rental basis. If a well is not viable for commercial production, the land will be restored and returned to the landowner.
Cost, jobs and schedule
The total cost of the project is estimated at ₹1,598.05 crore.
During the drilling operation, about 30 to 35 people will work in 12-hour shifts at each site. The pre-feasibility report states that preference in employment will be accorded to local residents.
The likely date to start construction activity is 1 January 2028, with completion expected by 31 December 2037.
Water, power and connectivity
Water is required only during the drilling phase. Each well will consume 22 kilolitres per day (KLD) for 30 to 60 days. The water will be sourced from ONGC's water treatment plant and transported by tankers.
Power to operate the rig will be supplied by four 1,430 KVA diesel generator (DG) sets (including one standby) and one 100 KVA DG set at each well. Each well will consume 4 to 5 KLD of high-speed diesel.
The operational area is connected by state and national highways, other district roads and railways. Approach roads will be planned to well sites that are not currently connected.
Environmental concerns and safeguards
ONGC proposes to use a water-based mud (WBM) system for drilling. The mud will flush out formation cuttings from the well hole. The cuttings will be separated from the drilling mud using shale shakers and centrifuges. The recovered mud will be reused in a closed-loop system, while the rejected solids will be collected and discharged into a specially designed waste pit lined with high-density polyethylene (HDPE).
Each well will generate 5 KLD of wastewater from washing drill cuttings and rig equipment. This will be treated in a 50 KLD mobile effluent treatment plant (ETP) and the treated water will be reused for washing activities at the drill site. Domestic sewage will be treated in a septic tank with a soak pit.
During production, wastewater generated from the installations will be treated in existing ETPs at CTF Ankleshwar, CPF Gandhar and EPS Nada, and disposed of in injection or disposal wells.
To control air pollution, the DG sets will have a stack height of 7.5 metres. Acoustic enclosures will be provided for the DG sets, and engine exhausts will be fitted with silencers to mitigate noise.
Approvals so far
The project requires environmental clearance from the Ministry of Environment, Forest and Climate Change. ONGC has applied for the Terms of Reference (ToR) to conduct an Environmental Impact Assessment (EIA) study. The application was filed on 6 November 2026 and is currently under environmental review.
Filings for this project
| Filing | Approval sought | Status | Filed | Status since |
|---|---|---|---|---|
| Onshore Development and Production of Oil & gas from 78 wells in 12 ML and 1… Early planning · Achhod, Amod, Bharuch | Environmental approval | Under environmental review | 6 Nov 2026 | 20 Nov 2026 |
Statuses update automatically twice a day.
About this page
Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.