Nagpur Mumbai Super Communication Expressway Limited proposes to expand the eastern alignment of the Pune Ring Road (Part 2) in Pune district, Maharashtra. The 68.841 km expressway will start from Solu village and end at Khopi village, passing through 29 villages across Khed, Haveli, Purandhar, and Bhor talukas. The project aims to decongest Pune city by diverting external traffic. The estimated cost is ₹15,980 crore. The project is currently under environmental review.
| Item | Detail |
|---|---|
| Applicant | Nagpur Mumbai Super Communication Expressway Limited |
| Length | 68.841 km |
| Lanes | 6 (3+3) divided carriageway |
| Right of Way | 100 metres |
| Total Land | 711.5221 hectares |
| Forest Land | 75.1120 hectares |
| Estimated Cost | ₹15,980 crore |
| Construction Period | 36 months |
What is planned
The proposed expansion involves a 68.841 km expressway with a 100-metre right of way (ROW). It will feature a six-lane divided carriageway (3+3 lanes) with a central median width of approximately 15 metres. The design speed is up to 120 kmph.
The project includes the construction of:
- 109 box culverts
- 6 CUP/PUPs (Cattle/Pedestrian Underpasses)
- 7 flyovers
- 3 interchange flyovers
- 5 major bridges
- 27 minor bridges
- 3 ROBs (Railway Over Bridges)
- 28 VUPs (Vehicular Underpasses)
- 14 LVUPs (Light Vehicular Underpasses)
- 6 VOPs (Vehicular Overpasses)
- 4 tunnels
Six interchanges are planned at Lonikand, Koregaon, Walati, Dive-Chambali, Shivare, and Khopi. A closed-loop toll system will be adopted.
Where it is and the land
The alignment starts at Solu village (CH 38+340) and ends at Khopi village (CH 107+181). It passes through 29 villages: Solu, Markal, Golegaon, Tulapur, Bhawadi, Lonikand, Perane, Bakori, Dongargaon, Wade Bolhai, Gawdewadi, Murkutenagar, Biwari, Pragdham, Koregaon Mul, Shindwane, Walati, Tarade, Alandi Mhatobachi/Ramoshiwadi, Sonori, Kalewadi, Dive, Hivare, Chambali, Kodit Kh., Garade, Thapewadi, Shivare, and Khopi.
The total land requirement is 711.5221 hectares, comprising 509.6867 hectares of private land, 38.8234 hectares of government land, and 75.1120 hectares of forest land. The terrain is mostly plain, with some hilly sections. The predominant land use is agricultural, followed by residential, commercial, and mixed built-up areas.
Cost, jobs and schedule
The estimated civil cost of the project is ₹15,980 crore. The construction period is expected to be 36 months after obtaining environmental clearance and other statutory approvals. The project will generate employment for approximately 600 people during the construction phase and about 50 people during the operation phase (for toll plazas).
Water, power and connectivity
During construction, the water requirement will be approximately 42,90,476 KL, with an additional 27 KLD needed for the 600 workers. Water will be sourced from water tankers or the Indrayani and Mula rivers, subject to necessary consents. Power for onsite construction and labour camps will be supplied by LSD D.G. sets where grid supply is unavailable.
Environmental concerns and safeguards
The project involves the diversion of 75.1120 hectares of forest land. The applicant's EIA report notes the presence of one endangered plant species (Tectona grandis) and one near-threatened reptile species (Varanus bengalensis) in the area. Two vulnerable mammal species, the Indian leopard (Panthera pardus) and the Bonnet macaque (Macaca radiata), were recorded in the study area, though not sighted within the proposed ROW.
To mitigate impacts, the applicant proposes a budget of ₹112 crore for environmental protection. Measures include regular water sprinkling to control dust, acoustic barriers for high-noise equipment, and routing surface runoff into small bunds to check for contamination. Rainwater harvesting will be implemented, and tree plantation will be undertaken along the alignment.
What was said at the public hearing
During the public hearing in Pune district, concerns were raised about contractors working on private lands without prior consent. The project proponent assured that contractors would be strictly instructed to work only within the approved project boundary and officially acquired land. A formal grievance redressal mechanism will be established.
Questions were also raised regarding dust pollution control and plantation. The proponent stated that mitigation measures, including regular water sprinkling and covering construction materials, would be implemented. Large-scale plantation will be undertaken along both sides of the road, and green buffer zones will be developed where feasible.
Approvals so far
The project was granted Standard Terms of Reference (ToR) by the State Expert Appraisal Committee-1 (SEAC-1) on October 19, 2025. It is currently under environmental review. An earlier environmental clearance was granted on January 9, 2023, for a 66.560 km length of the project.
Filings for this project
| Filing | Approval sought | Status | Filed | Status since |
|---|---|---|---|---|
| Proposed Expansion of Pune Ring Road, Eastern Alignment (Part 2) Early planning · Alandi (Mhatobachi), Haveli, Pune | Environmental approval | Cleared for impact study | 31 Aug 2025 | 19 Oct 2025 |
| Proposed Expansion of Pune Ring Road, Eastern Alignment (Part 2) Expansion · Alandi (Mhatobachi), Haveli, Pune | Environmental approval | Under environmental review | 21 Oct 2026 | 27 Oct 2026 |
Statuses update automatically twice a day.
About this page
Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.