Feature · Latehar, Jharkhand

RVNL Kumandih-Barwadih Railway Diversion: 18.5 km Railway Line in Latehar, Jharkhand

Rail Vikas Nigam Limited proposes an 18.5 km railway diversion costing ₹1,223.35 crore to bypass the Palamau Tiger Reserve core area in Latehar, Jharkhand.

Where it stands: Diversion of the entire Railway network between Kumandih and Barwadih (18.5 km) away… — “Withdrawn” since 8 Nov 2026. 4 related filings are listed below. Status data as of 27 Nov 2026, 6:36 am IST.

Rail Vikas Nigam Limited (RVNL) is proposing the diversion of the entire railway network between Kumandih and Barwadih to route it away from the Palamau Tiger Reserve. The 18.5 km project is located across villages including Gua, Hehegara, Kope, Lanka, Kerh, Gari, Chhipadohar, Kuchila, and Ukamar in the Barwadih sub-district of Latehar district, Jharkhand. The project is estimated to cost ₹1,223.35 crore. The proposal is currently under forest review.

ItemDetail
ApplicantRail Vikas Nigam Limited (RVNL)
Project length18.5 km
Estimated cost₹1,223.35 crore
Total land (latest filing)13,589.83 hectares (33,581.46 acres)
Forest land (latest filing)77.135 hectares (190.6 acres)

What is planned

According to the justification document filed with the application, the project is part of the Patratu–Sonnagar Third Line Project. The existing railway network passes through the core area of the Palamau Tiger Reserve (PTR), which imposes a speed restriction of 35 km/h and presents risks to wildlife. To address this, RVNL proposes "Alternative Alignment-3" to divert the tracks outside the core area.

The proposed alignment will feature three railway tracks, with a provision for a fourth line. It will commence at Km 236.80 of the existing alignment and rejoin it at Km 255.20. The project includes the construction of new railway stations to maintain connectivity and serve passenger footfall. A proposed Hehegara Railway Station is planned at Km 238.84, featuring 600-metre-long platforms. A new station is also proposed at Kerh village at Km 246.26 to serve the Betla National Park area. Additionally, a proposed Chhipadohar Railway Station is planned at Km 253.70, located approximately 1.0 to 1.65 km from the existing station.

Where it is and the land

The most recent forest clearance filing states that the project requires a total of 13,589.83 hectares (33,581.46 acres) of land, including 77.135 hectares (190.6 acres) of forest land. However, an earlier project justification document submitted by the applicant gives a different figure, stating a total land requirement of 155 hectares (383 acres). According to this document, the 155 hectares comprise 39.191 hectares in the Palamau Tiger Reserve, 37.944 hectares under the Divisional Forest Officer (DFO) Latehar, 33.377 hectares of government land, and 44.486 hectares of private or non-forest land.

Once the diversion is completed, the applicant proposes to vacate approximately 130.67 hectares (322.88 acres) of existing railway land within the PTR core area. The tracks and structures will be removed, and the land will be transferred to the forest department for ecological restoration.

Environmental concerns and safeguards

The project documents outline several measures to mitigate the impact on wildlife and maintain natural movement corridors. According to the mitigation plan, a major bridge-cum-viaduct is proposed at Km 240.84, which will incorporate a wildlife passage of approximately 160 metres.

The alignment will cross the Auranga River at two locations. At Km 242.49, a major bridge-cum-viaduct will include wildlife passages of 78 metres and 145 metres on either side. At Km 245.30, another bridge across the river will feature passages of 75 metres and 140 metres.

In the "Chicken Neck" area of the tiger reserve, the applicant proposes two underground tunnels to facilitate wildlife movement. These tunnels, located between Km 248.840 and Km 249.840, will each accommodate two railway tracks and have a length of approximately 1,000 to 1,500 metres.

Approvals so far

The project requires both forest and wildlife clearances. The applicant filed for wildlife clearance in September 2026, and the application is currently filed. Multiple applications for forest clearance were submitted in September and October 2026. While earlier forest filings were not approved, the most recent application filed on October 13, 2026, is currently under forest review.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Diversion of the entire Railway network between Kumandih and Barwadih (18.5…
New project · Ker, Barwadih, Latehar
Forest land useNot approved8 Sept 20261 Oct 2026
Diversion of the entire Railway network between Kumandih and Barwadih (18.5…
New project · Ker, Barwadih, Latehar
Forest land useNot approved8 Sept 20261 Oct 2026
Diversion of the entire Railway network between Kumandih and Barwadih (18.5…
New project · Gua, Barwadih, Latehar
Wildlife reviewWithdrawn9 Sept 20268 Nov 2026
Diversion of the entire Railway network between Kumandih and Barwadih (18.5…
New project · Ker, Barwadih, Latehar
Forest land useUnder forest review13 Oct 20264 Nov 2026

Statuses update automatically twice a day.

About this page

Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.