What is Developing? Open the mapMap

Feature · Jajpur, Odisha

Tata Steel Plans a 10-Million-Tonne Expansion at Kalinganagar, Odisha

Tata Steel Limited has proposed expanding its Kalinganagar integrated steel plant in Jajpur, Odisha, from 8 to 18 million tonnes per annum at an estimated cost of ₹1,33,761.16 crore.

Where it stands: Expansion of Integrated Steel Plant from 8 MTPA Crude Steel & 9 MTPA Finished Steel to… — “More information requested” since 23 Nov 2026. Status data as of 27 Nov 2026, 6:36 am IST.

Tata Steel Limited proposes to expand its integrated steel plant at the Kalinganagar Industrial Complex near Duburi village, Sukinda tehsil, Jajpur district, Odisha. The expansion will increase the plant's crude steel production capacity from 8 MTPA (million metric tonnes per annum) to 18 MTPA, and its finished steel capacity from 9 MTPA to 19 MTPA. According to the latest filing, the project is estimated to cost ₹1,33,761.16 crore. The application for environmental clearance is currently at the stage where more information has been requested.

ItemDetail
ApplicantTata Steel Limited
LocationKalinganagar, Jajpur, Odisha
Proposed Capacity18 MTPA crude steel, 19 MTPA finished steel
Estimated Cost₹1,33,761.16 crore
Land Area1,250 hectares (3,088.8 acres)

What is planned

According to the pre-feasibility report filed with the application, the expansion will add 10 MTPA of crude steel capacity through the blast furnace and basic oxygen furnace route. The final configuration will include four blast furnaces, expanded coke ovens and by-product recovery plants, three sinter plants, two pellet plants, and a steel melt shop with seven slab casters. Downstream facilities will include two hot strip mills, a plate mill, a thin slab caster and rolling mill, and two cold rolling mills. The project will require 3,68,36,000 tonnes of raw materials annually, including iron ore, coking coal, and limestone, sourced from the company's own mines, domestic markets, and imports.

Where it is and the land

The project is located within the Kalinganagar Industrial Complex in Jajpur district. The pre-feasibility report notes that the expansion will be carried out on 1,250 hectares (3,088.8 acres) of existing contiguous lease land already available to the company. The site is bounded by the Brahmani river to the south and the Ganda nala to the north and east.

Cost, jobs and schedule

The most recent filing places the project cost at ₹1,33,761.16 crore, though an earlier pre-feasibility report estimated the capital cost at ₹83,700 crore. The applicant expects the expansion to generate 35,000 jobs. During the operation phase, this includes 4,900 direct and 14,600 indirect jobs. The construction phase will employ 500 people directly and 15,000 indirectly. The proposed project is scheduled to be completed within 96 months (eight years) from the grant of environmental and establishment clearances.

Water, power and connectivity

The expansion will require an additional 5,080 cubic metres per hour of water, bringing the total plant requirement to 9,560 cubic metres per hour. Raw water will be sourced from the Kharsua river, located 17 kilometres away at Marthapur village. The additional power requirement is estimated at 995 MW. Of this, 377.5 MW will be generated internally through captive power plants using by-product gases, while the remaining 617.5 MW will be drawn from the external grid.

The site is connected by National Highway 53 on its western boundary and State Highway 20 on its northern boundary. The nearest railway station is Sukinda Road, located 1.1 kilometres away, and the Jakhapura railway station is 11 kilometres away. The nearest seaport is Paradeep, about 120 kilometres from the site.

Environmental concerns and safeguards

The pre-feasibility report identifies particulate dust, sulphur dioxide, nitrogen oxides, and carbon dioxide as key air pollutants. To mitigate these, the applicant proposes installing polytetrafluoroethylene bag filters, dry gas cleaning plants for the blast furnaces, and a pushing emission control system for the coke ovens.

Wastewater from the coke ovens, cold rolling mill, and other facilities will be treated in dedicated effluent treatment plants, a central effluent treatment plant, and a sewage treatment plant. The treated water will be recycled for plant use. Solid wastes, such as blast furnace slag, will be granulated and sold to cement manufacturers, while dust and sludge will be reused internally in the sinter and pellet plants.

Approvals so far

The project previously received environmental clearance in 2020 to expand from 6 MTPA to 8 MTPA. For the current 18 MTPA expansion proposal, the environmental clearance application is at the stage where more information has been requested.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Expansion of Integrated Steel Plant from 8 MTPA Crude Steel & 9 MTPA Finished…
Early planning · Gobara Gh>Ti, Kalinganagar, Jajapur
Environmental approvalMore information requested19 Nov 202623 Nov 2026

Statuses update automatically twice a day.

About this page

Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.