The National Highways Authority of India (NHAI) proposes to build a six-lane elevated highway corridor along the Varuna River to decongest Varanasi city in Uttar Pradesh. The project, starting from National Highway-31 (NH-31) and ending at the Kashi Railway Station, will span Varanasi Cantt and surrounding areas in the Sadar sub-district of Varanasi. The 43.21-km project (including ramps and service roads) is estimated to cost ₹10,998.32 crore. It is currently under environmental review.
| Item | Detail |
|---|---|
| Applicant | National Highways Authority of India |
| Total length | 43.218 km |
| Main carriageway | 19.420 km |
| Estimated cost | ₹10,998.32 crore |
| Land required | 277.24 hectares (685 acres) |
What is planned
According to the pre-feasibility and environmental impact assessment (EIA) reports, the NHAI plans to construct a six-lane divided elevated viaduct under the Hybrid Annuity Mode (HAM). While the main carriageway will be 19.420 km long, the total length including the main carriageway, flyovers, loops, ramps, and service roads will be 43.218 km.
The corridor will start at NH-31 (Varanasi-Lucknow road) and terminate near the Kashi Railway Station. It is designed to ease traffic congestion in Varanasi by providing a dedicated, high-capacity transit facility that minimizes traffic interference at the ground level. The alignment will feature five major bridges and four railway overbridges (ROBs). The viaduct will be elevated 6 to 12 metres above ground level to ensure it remains above the flood zone of the Varuna River. The alignment will also feature two-level interchanges and approaches on cross roads at Harhua Junction, with ramps provided at Phulwariya Tiraha and Chaukaghat.
Where it is and the land
The alignment primarily follows a greenfield route along the Varuna River, passing through settlements such as Harhua, Pissaur, Phulwariya, Victory Bridge, Chaukaghat, and the Varanasi city railway station area. The topography of the district is characterized by a flat, highly fertile alluvial terrain within the central Indo-Gangetic Plain.
According to the most recent environmental filing, the project requires 277.24 hectares (685 acres) of land. An earlier EIA report mentioned a total area of 138.7 hectares (342.7 acres), comprising agricultural land, surface water bodies, and settlements. The project also involves the diversion of 0.98 hectares (2.4 acres) of forest land. Around 3.22 hectares (7.9 acres) of Defence land is affected, for which working permission has been obtained.
Cost, jobs and schedule
The most recent environmental filing estimates the project cost at ₹10,998.32 crore, up from an earlier estimate of ₹8,872.63 crore. The EIA report specifies that the base civil construction cost is ₹4,565.33 crore, with the total engineering, procurement, and construction (EPC) cost reaching the higher figure when including GST, contingencies, and supervision charges.
The project is expected to take four years to construct. During the construction phase, it will generate approximately 40 permanent and 400 temporary or contractual jobs. Once operational, it will employ about 20 permanent and 30 temporary personnel.
Environmental concerns and safeguards
The EIA report states that 995 trees will be felled for the project. To mitigate this, compensatory afforestation will be carried out by the state forest department at a ratio of 1:10.
Because the alignment runs along the Varuna River flood plain, the Alignment Approval Committee recommended an elevated structure to maintain the natural floodplain and ensure the unobstructed flow of floodwaters. The project will require about 300 KLD (kilolitres per day) of water during construction and 20 KLD during operation, which will be sourced from surface and groundwater after obtaining necessary permissions.
Approvals so far
The project is currently under environmental review by the Ministry of Environment, Forest and Climate Change. A separate application for forest clearance was filed in July 2026, and authorities requested more information in October 2026.
Filings for this project
| Filing | Approval sought | Status | Filed | Status since |
|---|---|---|---|---|
| Link/Connector Corridor Connecting the National Highway-31 (NH-31) & Varanasi… Early planning · Varanasi Cantt, Sadar, Varanasi | Environmental approval | Under environmental review | 26 Jun 2026 | 19 Nov 2026 |
| Link/Connector Corridor Connecting the National Highway-31 (NH-31) & Varanasi… New project · Ausanpur, Pindra, Varanasi | Forest land use | More information requested | 22 Jul 2026 | 16 Oct 2026 |
| Link/Connector Corridor Connecting the National Highway-31 (NH-31) & Varanasi… New project · Varanasi Cantt, Sadar, Varanasi | Environmental approval | Under environmental review | 19 Nov 2026 | 20 Nov 2026 |
Statuses update automatically twice a day.
About this page
Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.