Feature · Vijayapura, Karnataka

Vijayapura Airport: A ₹348-Crore Greenfield Project in Karnataka

The Karnataka State Industrial & Infrastructure Development Corporation is building a greenfield airport on 294.2 hectares in Vijayapura, Karnataka, to handle 459 peak-hour passengers.

Where it stands: Development of Greenfield Airport at Vijayapura, Karnataka — “Under environmental review” since 12 Nov 2026. 2 related filings are listed below. Status data as of 27 Nov 2026, 6:36 am IST.

The Karnataka State Industrial & Infrastructure Development Corporation Limited is building a greenfield airport at Aliyabad, Burnapur, and Madabhavi villages in Vijayapura district, Karnataka. The project, spread over 294.2 hectares (727 acres), is designed to handle 459 peak-hour passengers in its first phase. The estimated cost is ₹347.92 crore. The project is currently under environmental review, having applied for clearance under the violation category because construction began before approval was granted.

ItemDetail
Land area294.2 hectares (727 acres)
Peak-hour capacity459 passengers
Runway length3,000 metres
Estimated cost₹347.92 crore
Water requirement132 KLD

What is planned

According to the EIA report and summary documents, the project involves constructing a 3,000-metre by 45-metre runway, suitable for Airbus A321 Neo and Boeing 737-900 aircraft. The runway will have a 3,120-metre by 288-metre strip and 60-metre blast pads at both ends.

The airport will feature a 4,395-square-metre domestic terminal building, centrally air-conditioned and capable of handling 200 arriving and 259 departing passengers during peak hours. Other planned facilities include:

The airport is planned to be developed in three phases, with the first phase detailed in the current application.

Where it is and the land

The site is located in Vijayapura taluk, about 10 kilometres southwest of Vijayapura city. The land, covering 294.2 hectares, has already been acquired. The topography is mostly flat, with elevations ranging from 540 to 584 metres above mean sea level.

The EIA report notes that village roads leading to Aliyabad and Dyaberi are being diverted or re-routed around the site. A small ephemeral drain passing through the runway area is being strengthened with culverts to maintain its flow.

Cost, jobs and schedule

The total estimated cost of the project is ₹347.92 crore. The EIA report states that the project will provide direct employment for 700 people during the construction phase and 283 people during the operational phase. The construction is expected to be completed within 24 months from the date of environmental clearance.

Water, power and connectivity

The airport will require 132 kilolitres per day (KLD) of water during operation, which will be sourced from the Karnataka Urban Water Supply and Drainage Board. During construction, about 45 KLD of water is needed, supplied by private tankers.

Power will be drawn from the Hubli Electricity Supply Company Limited, with a total connected load of 2,000 kVA. Three 500 kVA diesel generator sets will provide backup power. A 150 kW solar power plant is also proposed.

The site is connected by National Highway 50 (Hubli-Vijayapura-Gulbarga), located 2.79 kilometres to the south, and National Highway 52 (Bijapur Bypass), 6.5 kilometres to the south-southwest. The nearest railway station is Vijayapura, 6.92 kilometres away.

Environmental concerns and safeguards

The project is applying for environmental clearance under the violation category because construction started before prior approval was obtained. The EIA report calculates an environmental compensation of ₹3.47 crore (1% of the project cost) for ecological remediation and resource augmentation.

To manage environmental impacts, the applicant proposes:

What was said at the public hearing

Minutes from the public hearing show that local residents raised concerns about road connectivity, particularly the diversion of roads to Dyaberi and other villages. Officials explained that alternative routes are being provided and that land acquisition for new roads is underway.

Residents also requested improvements to the road connecting the Indian Oil Corporation depot to Gunnapur and the airport. Officials stated that ₹19.70 crore has been sanctioned for this road's development. Other requests included addressing fly nuisance from a nearby godown, constructing compound walls for schools and a veterinary hospital, and building additional classrooms and libraries in project-affected villages.

Approvals so far

The project was cleared for an environmental impact study on October 23, 2023, under the violation category. It is currently under environmental review.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Development of Greenfield Airport at Vijayapura, Karnataka
Early planning · Aliyabad, Vijayapura, Vijayapura
Environmental approvalCleared for impact study2 Sept 202323 Oct 2023
Development of Greenfield Airport at Vijayapura, Karnataka
New project · Aliyabad, Vijayapura, Vijayapura
Environmental approvalUnder environmental review7 Oct 202612 Nov 2026

Statuses update automatically twice a day.

About this page

Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.