Where they are in the approval process
| Status | Projects |
|---|---|
| Filed or under review | 5 |
| Approved | 48 |
| Withdrawn or lapsed | 3 |
Recently approved
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| 4.480ha Morrum/Gravel/Ordinary Earth Mine of M/s. Megha Engineering Infrastructures… Kondapavuluru, Gannavaram | Mining | 11.1 acres | Environmental approval granted | 10 Sept 2026 |
| Sri Tummala Lakshmana Rao – 1.618 Ha Gopavarapugudem, Gannavaram | Mining | 4 acres | Environmental approval granted | 7 Jul 2026 |
| Mining project by M/s RP Enterprises Vedurupavluru, Gannavaram | Mining | 10.7 acres | Environmental approval granted | 23 Apr 2026 |
| Mining project by M/S. Unique Enterprises, Mg.P:Sri.Gummadi Naganjaneyulu(4.634 Ha) Metlapalle, Gannavaram | Mining | 11.4 acres | Environmental approval granted | 23 Jun 2026 |
| Sri Vuyyuru Venkata Bharat Vedurupavluru, Gannavaram | Mining | 12.2 acres | Environmental approval granted | 9 Jun 2026 |
| Sri Tummala Motilal Chandu Devarapalle, Thotlavalluru | Mining | 4 acres | Environmental approval granted | 20 May 2026 |
| Mining project by M/s Larsen & Toubro Limited Vedurupavuluru, Gannavaram | Mining | 15.2 acres | Environmental approval granted | 23 Mar 2026 |
| Mining project by M/s Larsen & Toubro Limited Vedurupavuluru, Gannavaram | Mining | 15.2 acres | Cleared for impact study | 25 Nov 2025 |
| Srikakulam Sand Reach Srikakulam, Ghantasala | Mining | 74.1 acres | Environmental approval granted | 24 Mar 2026 |
| Madduru Sand Reach Madduru, Thotlavalluru | Mining | 14.8 acres | Environmental approval granted | 24 Mar 2026 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Mining project by 4.00 ha NRSKS MINES AND MINERALS PRIVATE LIMITED Gollanapalle, Gannavaram | Mining | 9.9 acres | More information requested | 27 Oct 2026 |
| Sri Kalagara Pradeep Kumar Ranganagudem, Bapulapadu | Mining | 4.1 acres | Under environmental review | 12 Oct 2026 |
| Mining project by M/s Armuuga Constructions Private Limited Vedurupavluru, Gannavaram | Mining | 35.3 acres | Under environmental review | 6 Oct 2026 |
| 4.480ha Morrum/Gravel/Ordinary Earth Mine of M/s. Megha Engineering Infrastructures… Kondapavuluru, Gannavaram | Mining | 11.1 acres | Environmental approval granted | 10 Sept 2026 |
| Sri Tummala Lakshmana Rao – 1.618 Ha Gopavarapugudem, Gannavaram | Mining | 4 acres | Environmental approval granted | 7 Jul 2026 |
| Mining project by M/S. Unique Enterprises, Mg.P:Sri.Gummadi Naganjaneyulu(4.634 Ha) Metlapalle, Gannavaram | Mining | 11.4 acres | Environmental approval granted | 23 Jun 2026 |
| Sri Vuyyuru Venkata Bharat Vedurupavluru, Gannavaram | Mining | 12.2 acres | Environmental approval granted | 9 Jun 2026 |
| Sri Tummala Motilal Chandu Devarapalle, Thotlavalluru | Mining | 4 acres | Environmental approval granted | 20 May 2026 |
| Mining project by M/s RP Enterprises Vedurupavluru, Gannavaram | Mining | 10.7 acres | Environmental approval granted | 23 Apr 2026 |
| SRI S. LH. BHARADWAJ, (Gravel / Ordinary Earth Quarry : 1.620 Hectares) Kondapavuluru, Gannavaram | Mining | 4 acres | Under environmental review | 31 Mar 2026 |
| Additional Exploratory Drilling Of45 Wells in West Godavari, Malleswaram and Nandigama… Addada, Pamarru | Mining | 3,52,124.6 acres | Environmental approval granted | 27 Mar 2026 |
| Srikakulam Sand Reach Srikakulam, Ghantasala | Mining | 74.1 acres | Environmental approval granted | 24 Mar 2026 |
| Madduru Sand Reach Madduru, Thotlavalluru | Mining | 14.8 acres | Environmental approval granted | 24 Mar 2026 |
| Northvalluru-2 Sand Reach North Valluru, Thotlavalluru | Mining | 74.1 acres | Environmental approval granted | 24 Mar 2026 |
| Royyuru-2 Sand Reach Royyuru, Thotlavalluru | Mining | 74.1 acres | Environmental approval granted | 24 Mar 2026 |
| Chodavaram-2 Sand Reach Chodavaram, Penamaluru | Mining | 74.1 acres | Environmental approval granted | 24 Mar 2026 |
| Lankapalli – 2 Sand Reach Lankapalle, Pamidimukkala | Mining | 86.5 acres | Environmental approval granted | 24 Mar 2026 |
| Mining project by M/s Larsen & Toubro Limited Vedurupavuluru, Gannavaram | Mining | 15.2 acres | Environmental approval granted | 23 Mar 2026 |
| Madduru Sand Reach Madduru, Thotlavalluru | Mining | 14.8 acres | Cleared for impact study | 20 Jan 2026 |
| Lankapalli – 2 Sand Reach Lankapalle, Pamidimukkala | Mining | 86.5 acres | Cleared for impact study | 20 Jan 2026 |
| Northvalluru-2 Sand Reach North Valluru, Thotlavalluru | Mining | 74.1 acres | Cleared for impact study | 20 Jan 2026 |
| Srikakulam Sand Reach Srikakulam, Ghantasala | Mining | 74.1 acres | Cleared for impact study | 20 Jan 2026 |
| Royyuru-2 Sand Reach Royyuru, Thotlavalluru | Mining | 74.1 acres | Cleared for impact study | 20 Jan 2026 |
| Chodavaram-2 Sand Reach Chodavaram, Penamaluru | Mining | 74.1 acres | Cleared for impact study | 20 Jan 2026 |
| Onshore Development & Production of oil and gas from 12wells and expansion of… Nagayalanka, Nagayalanka | Mining | 13,572.1 acres | Lapsed | 15 Jan 2026 |
| Mining project by M/s. BSR Infra Tech India Ltd – 4.50 Ha Purushottapatnam, Gannavaram | Mining | 11.1 acres | Environmental approval granted | 3 Jan 2026 |
| Mining project by M/s. BSR Infra Tech India Ltd – 4.700 Ha Kondapavuluru, Gannavaram | Mining | 11.6 acres | Environmental approval granted | 19 Dec 2025 |
| Mining project by M/s. RVR Projects Pvt Ltd – 4.950 Ha Kondapavuluru, Gannavaram | Mining | 12.2 acres | Environmental approval granted | 6 Dec 2025 |
| Mining project by M/s Larsen & Toubro Limited Vedurupavuluru, Gannavaram | Mining | 15.2 acres | Cleared for impact study | 25 Nov 2025 |
| Sri Dandamudi Nithin Kumar – 4.452 Ha Chodavaram, Penamaluru | Mining | 11 acres | Environmental approval granted | 11 Nov 2025 |
| De casting of Sand from Pattalands Srikakulam, Ghantasala | Mining | 5.2 acres | Environmental approval granted | 13 Oct 2025 |
| Papavinasanam Sand Reach Srikakulam, Ghantasala | Mining | 25.5 acres | Environmental approval granted | 2 Jun 2025 |
| Chodavaram Sand Reach Chodavaram, Penamaluru | Mining | 17.3 acres | Environmental approval granted | 12 Mar 2025 |
| Patamatalanka Sand Reach Lankapalle, Pamidimukkala | Mining | 37.1 acres | Environmental approval granted | 12 Mar 2025 |
| Royyuru Sand Reach Royyuru, Thotlavalluru | Mining | 61.8 acres | Environmental approval granted | 12 Mar 2025 |
| Northvalluru Sand Reach North Valluru, Thotlavalluru | Mining | 61.8 acres | Environmental approval granted | 11 Mar 2025 |
| Mining project by M/s Venkateswara Constructions, Mg.Ptr: Sri Raghu Rama Rao (4.046 Ha) Savaragudem, Gannavaram | Mining | 10 acres | Lapsed | 4 Feb 2025 |
| Papavinasanam Sand Reach Srikakulam, Ghantasala | Mining | 25.5 acres | Cleared for impact study | 26 Oct 2024 |
| Chodavaram Sand Reach Chodavaram, Penamaluru | Mining | 17.3 acres | Cleared for impact study | 26 Oct 2024 |
| Royyuru Sand Reach Royyuru, Thotlavalluru | Mining | 61.8 acres | Cleared for impact study | 26 Oct 2024 |
| Northvalluru Sand Reach North Valluru, Thotlavalluru | Mining | 61.8 acres | Cleared for impact study | 26 Oct 2024 |
| Papavinasanam Sand Reach Srikakulam, Ghantasala | Mining | 25.5 acres | Withdrawn | 26 Oct 2024 |
| Patamatalanka Sand Reach Lankapalle, Pamidimukkala | Mining | 37.1 acres | Cleared for impact study | 26 Oct 2024 |
| 4.00 Ha. of Building Stone, Rough Stone & Gravel Quarry of Sri Anne Hari Krishna (Block… Gollanapalle, Gannavaram | Mining | 9.9 acres | Environmental approval granted | 23 Jan 2024 |
| 1.920 Hect. of Building Stone, Rough Stone & Gravel mine of Smt. Vallurupalli Satya… Vedurupavluru, Gannavaram | Mining | 4.7 acres | Environmental approval granted | 9 Dec 2023 |
| 2.60 Ha of Madduru-2, Ordinary Sand Extraction Madduru, Thotlavalluru | Mining | 6.4 acres | Environmental approval granted | 14 Nov 2023 |
| 4.900 Ha of Srikakulam-5, Ordinary Sand Extraction Srikakulam, Ghantasala | Mining | 12.1 acres | Environmental approval granted | 14 Nov 2023 |
| 4.900 Ha of Srikakulam-3, Ordinary Sand Extraction Srikakulam, Ghantasala | Mining | 12.1 acres | Environmental approval granted | 14 Nov 2023 |
| 4.50 Ha of Royyuru– 5, Ordinary sand extraction Royyuru, Thotlavalluru | Mining | 11.1 acres | Environmental approval granted | 14 Nov 2023 |
| 4.900 Ha of Royyuru-1, Ordinary Sand Extraction Royyuru, Thotlavalluru | Mining | 12.1 acres | Environmental approval granted | 14 Nov 2023 |
Questions people ask
How many mining projects are planned in Krishna?
56 mining projects in Krishna have applied for approval since January 2022. 53 of them are active (not withdrawn, lapsed or rejected) and 5 are still awaiting a decision.
What was approved most recently in Krishna?
4.480ha Morrum/Gravel/Ordinary Earth Mine of M/s. Megha Engineering Infrastructures Ltd., Authorized Person Uduthuri Saida Reddy in Kondapavuluru — “Environmental approval granted” on 31 Oct 2026.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.