Projects by type
| Type | Projects |
|---|---|
| Water & irrigation | 7 |
| Power | 7 |
| Roads & highways | 3 |
| Other | 1 |
| Telecom | 1 |
Where they are in the approval process
| Status | Projects |
|---|---|
| Filed or under review | 3 |
| Approved | 10 |
| Not approved | 1 |
| Withdrawn or lapsed | 5 |
Recently approved
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Kalai II Hydro Electric Project Chenguinty, Hawai Hq | Power | 3,836.1 acres | Forest land use approved | 22 Jan 2026 |
| Kalai II Hydro Electric Project Chenguinty, Hawai Hq | Water & irrigation | 7,178.5 acres | Environmental approval granted | 28 Nov 2025 |
| Diverion of 21.4 Ha of Forest Land for Construction of Manchal Pwd Road (Nenuliang) to… Manchal, Manchal Circle | Roads & highways | 52.9 acres | Forest land use approved | 16 Sept 2025 |
| 33 KV LINE FROM PROPOSED 33/11 KV HAWAI S/STN to PROPOSED 33/11 KV WALLONG S/STN 12th K.M. Camp, Hawai Hq | Power | 124.7 acres | Forest land use approved | 29 May 2023 |
| 33 KV Line From Proposed 33/11 KV Halaipani S/Stn to Proposed 33/11KV Hayulaing S/Stn Abohagam, Hayuliang Adc | Power | 128.3 acres forest land | Forest land use approved | 29 May 2023 |
| 33 KV Line From Proposed 33/11 KV Halaipani (Marbo) S/Stn to Proposed 33/11KV Halaipani… Blong, Hawai Hq | Power | 44.5 acres | Forest land use approved | 29 May 2023 |
| 33 KV Line From Proposed 33/11 KV Hallaipani (Marbo) S/Stn to Proposed 33/11 KV Hawai… 9th K.M. Camp, Hawai Hq | Power | 26.2 acres | Forest land use approved | 28 May 2023 |
| Demwe Lower Hydroelectric Project Yealing, Hayuliang Adc | Water & irrigation | 3,928.9 acres | Environmental approval granted | 9 Oct 2025 |
| Kalai II Hydro Electric Project Chenguinty, Hawai Hq | Water & irrigation | 7,178.5 acres | Cleared for impact study | 13 Jun 2025 |
| Kalai II Hydro Electric Project Kamdi, Hawai Hq | Water & irrigation | 7,178.5 acres | Cleared for impact study | 10 Apr 2024 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Construction of Defence Strategic Project at Hayuliang Air Field Ziro Point, Hayuliang Adc | Other | 86 acres | Under forest review | 21 Jul 2026 |
| Anjaw Hydro Electric Project (270MW) Bomna, Hayuliang Adc | Water & irrigation | 386.7 acres | Under forest review | 17 Feb 2026 |
| Kalai II Hydro Electric Project Chenguinty, Hawai Hq | Power | 3,836.1 acres | Forest land use approved | 22 Jan 2026 |
| Kalai II Hydro Electric Project Chenguinty, Hawai Hq | Water & irrigation | 7,178.5 acres | Environmental approval granted | 28 Nov 2025 |
| Demwe Lower Hydroelectric Project Yealing, Hayuliang Adc | Water & irrigation | 3,928.9 acres | Environmental approval granted | 9 Oct 2025 |
| Diverion of 21.4 Ha of Forest Land for Construction of Manchal Pwd Road (Nenuliang) to… Manchal, Manchal Circle | Roads & highways | 52.9 acres | Forest land use approved | 16 Sept 2025 |
| Kalai II Hydro Electric Project Chenguinty, Hawai Hq | Power | 0.2 acres forest land | Lapsed | 1 Jul 2025 |
| Kalai II Hydro Electric Project Chenguinty, Hawai Hq | Water & irrigation | 7,178.5 acres | Cleared for impact study | 13 Jun 2025 |
| Diverion of 21.4 Ha of Forest Land for Construction of Manchal Pwd Road (Nenuliang) to… Zapaliang, Hayuliang Adc | Roads & highways | 52.9 acres | Lapsed | 19 Mar 2025 |
| Kalai II Hydro Electric Project Kamdi, Hawai Hq | Water & irrigation | 7,143 acres | More information requested | 20 Jan 2025 |
| Diversion of 15 ha of forest land for construction of Manchal PWD Road (Nenuliang) to… Nenuliang, Hayuliang Adc | Roads & highways | 37.1 acres | Lapsed | 21 Aug 2024 |
| L030-Manchal PWD Road to (Nenuliang) to Zapaliang Abohagam, Hayuliang Adc | Telecom | 74.1 acres forest land | Not approved | 28 Jul 2024 |
| Kalai II Hydro Electric Project Kamdi, Hawai Hq | Water & irrigation | 7,178.5 acres | Cleared for impact study | 10 Apr 2024 |
| Kalai II Hydro Electric Project Kamdi, Hawai Hq | Water & irrigation | 7,178.5 acres | Lapsed | 4 Mar 2024 |
| 33 KV Line From Proposed 33/11 KV Halaipani S/Stn to Proposed 33/11KV Hayulaing S/Stn Abohagam, Hayuliang Adc | Power | 128.3 acres forest land | Forest land use approved | 29 May 2023 |
| 33 KV LINE FROM PROPOSED 33/11 KV HAWAI S/STN to PROPOSED 33/11 KV WALLONG S/STN 12th K.M. Camp, Hawai Hq | Power | 124.7 acres | Forest land use approved | 29 May 2023 |
| 33 KV Line From Proposed 33/11 KV Halaipani (Marbo) S/Stn to Proposed 33/11KV Halaipani… Blong, Hawai Hq | Power | 44.5 acres | Forest land use approved | 29 May 2023 |
| 33 KV Line From Proposed 33/11 KV Hallaipani (Marbo) S/Stn to Proposed 33/11 KV Hawai… 9th K.M. Camp, Hawai Hq | Power | 26.2 acres | Forest land use approved | 28 May 2023 |
| 33 KV Line From Proposed 33/11 KV Halaipani S/Stn to Proposed 33/11KV Hayulaing S/Stn Ampani Camp, Hayuliang Adc | Power | 128.3 acres forest land | Lapsed | 5 Apr 2023 |
Questions people ask
How many projects are planned in Anjaw?
19 projects in Anjaw have applied for approval since January 2022. 13 of them are active (not withdrawn, lapsed or rejected) and 3 are still awaiting a decision.
What was approved most recently in Anjaw?
Kalai II Hydro Electric Project in Chenguinty — “Forest land use approved” on 7 Jul 2026.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.