Power projects in Bhiwani, Haryana

5 power projects in Bhiwani district, Haryana, have applied for environmental, forest, wildlife or coastal approval since January 2022. 1 are still filed or under review, and 0 were filed in the last 30 days. Updated 27 Nov 2026.

Explore Bhiwani on the live map

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

5power projects
1filed or under review
0filed in the last 30 days

Where they are in the approval process

StatusProjects
Filed or under review1
Approved3
Withdrawn or lapsed1

Recently approved

ProjectTypeSizeStatusFiled
"Siwani - Sonipat 400 kV D/c Quad Conductor Transmission Line (TL03 Package)" For…
Jamalpur, Bawani Khera
Power5,607.1 acresForest land use approved20 Dec 2025
Diversion of Forest Land for Construction of 765kV D/c Bikaner-IV PS -Siwani…
Dhani Bhakran, Siwani
Power900.7 acresForest land use approved26 Jan 2026
765 kV D/c Bikaner-IV PS-Siwani Transmission line (Line- 1st) - Part I and Part-II in…
Dhani Bhakran, Siwani
Power918.8 acresForest land use approved26 Jan 2026

Recently filed

ProjectTypeSizeStatusFiled
Creation of 220KV D/C PGCIL Bhiwani - Dadhibana line on D/C tower with 0.5 Sq inch ACSER…
Ajitpur, Bhiwani
Power58.9 acresLapsed15 Apr 2026
765 kV D/c Bikaner-IV PS-Siwani Transmission line (Line- 1st) - Part I and Part-II in…
Dhani Bhakran, Siwani
Power918.8 acresForest land use approved26 Jan 2026
Diversion of Forest Land for Construction of 765kV D/c Bikaner-IV PS -Siwani…
Dhani Bhakran, Siwani
Power900.7 acresForest land use approved26 Jan 2026
"Siwani - Sonipat 400 kV D/c Quad Conductor Transmission Line (TL03 Package)" For…
Jamalpur, Bawani Khera
Power5,607.1 acresForest land use approved20 Dec 2025
Creation of Lilo of One Circuit of 132 KV D/C Dadibhana- Loharu Line at 132 KV S/Stn…
Gagarwas, Loharu
Power107.8 acresMore information requested23 Jan 2025

Questions people ask

How many power projects are planned in Bhiwani?

5 power projects in Bhiwani have applied for approval since January 2022. 4 of them are active (not withdrawn, lapsed or rejected) and 1 are still awaiting a decision.

What was approved most recently in Bhiwani?

"Siwani - Sonipat 400 kV D/c Quad Conductor Transmission Line (TL03 Package)" For evacuation of power from "Rajasthan REZ Ph-IV (Part-3:6 GW) (Bikaner Complex): Part B" through Tariff based Competitive bidding (TBCB) route at State of Haryana in Jamalpur — “Forest land use approved” on 6 Nov 2026.

How often is this list updated?

Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.