10power projects
6filed or under review
0filed in the last 30 days

Where they are in the approval process

StatusProjects
Filed or under review6
Approved3
Withdrawn or lapsed1

Recently approved

ProjectTypeSizeStatusFiled
New 33KV Line Bheempura under SSTD Scheme
Kothami, Sirali
Power151.8 acresForest land use approved22 Sept 2024
New 33KV Line Chandrakhal under SSTD Scheme
Jhirpi, Rehatgaon
Power21.3 acresForest land use approved17 Sept 2024
33/11 KV New Sub Station under SSTD Scheme
Chandarkhal, Rehatgaon
Power0.2 acresForest land use approved15 Jul 2024

Recently filed

ProjectTypeSizeStatusFiled
11 KV Keli DLF Task ID 639765 (FSP) in Rehatgaon D/c under RDSS scheme
Chandlyapura, Rehatgaon
Power275 acresMore information requested13 Oct 2026
11 KV Singoda DLF Task ID 643030 (FSP) in Sirali D/c under RDSS scheme
Malor, Harda
Power170.2 acresMore information requested29 Sept 2026
Interconnection work of 11 KV Churikhal feeder by Central Govt
Kumbhikhara, Sirali
Power109.6 acresMore information requested5 Jun 2025
New 11 KV Line for Chandrakhal
Jhirpi, Rehatgaon
Power339.9 acresMore information requested30 May 2025
11 KV Balagaon Interconnection work , Rehatgaon DC
Jawardha R F, Rehatgaon
Power8.6 acresLapsed29 Dec 2024
New 33KV Line Bheempura under SSTD Scheme
Kothami, Sirali
Power151.8 acresForest land use approved22 Sept 2024
New 33KV Line Chandrakhal under SSTD Scheme
Jhirpi, Rehatgaon
Power21.3 acresForest land use approved17 Sept 2024
New 33KV Line Chandrakhal under SSTD Scheme
Jhirpi, Rehatgaon
Power22.7 acresMore information requested10 Sept 2024
33/11 KV Sub Station under SSTD Scheme
Bhimpura, Sirali
Power5 acresMore information requested29 Aug 2024
33/11 KV New Sub Station under SSTD Scheme
Chandarkhal, Rehatgaon
Power0.2 acresForest land use approved15 Jul 2024

Questions people ask

How many power projects are planned in Harda?

10 power projects in Harda have applied for approval since January 2022. 9 of them are active (not withdrawn, lapsed or rejected) and 6 are still awaiting a decision.

What was approved most recently in Harda?

New 33KV Line Bheempura under SSTD Scheme in Kothami — “Forest land use approved” on 14 Aug 2026.

How often is this list updated?

Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.

Most active developers in Harda

Other districts in Madhya Pradesh