Where they are in the approval process
| Status | Projects |
|---|---|
| Filed or under review | 1 |
| Approved | 2 |
| Withdrawn or lapsed | 1 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| 765 kV Vindhyachal Pool- Prayagraj D/c line Kailashpur, Hanumana | Power | 2,688.4 acres | More information requested | 30 Apr 2026 |
| Augmentation Of waterSupply scheme for Industrial Park Gudh, R.F, Huzur | Power | 4.7 acres | Lapsed | 14 Jan 2026 |
| Transmission Lines associated with 400/220/132kV Substation in Gurh, Rewa Amilaki, Huzur | Power | 506 acres | Forest land use approved | 15 Dec 2025 |
| Village Gauri to Bari Chaura 33 KV Sub Transmission Line Daakra Bari Reserved Forest, Teonthar | Power | 773.6 acres | Forest land use approved | 15 Aug 2024 |
Questions people ask
How many power projects are planned in Rewa?
4 power projects in Rewa have applied for approval since January 2022. 3 of them are active (not withdrawn, lapsed or rejected) and 1 are still awaiting a decision.
What was approved most recently in Rewa?
Village Gauri to Bari Chaura 33 KV Sub Transmission Line in Daakra Bari Reserved Forest — “Forest land use approved” on 23 Nov 2026.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.