This week's digest: Mumbai & Thane: 7 New Project Filings Recorded
Where they are in the approval process
| Status | Projects |
|---|---|
| Filed or under review | 4 |
| Approved | 3 |
| Withdrawn or lapsed | 4 |
Recently approved
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Retaining wall at boundary of Pandit Deen Dayal Upadhyay Garden Near Windermere CHS CTS… Greater Mumbai (M Corp.), Mumbai Suburban | Power | 0.2 acres | Recommended by coastal authority | 16 Jul 2025 |
| 33 KV Multi Circuit Transmission Tower line at Gorai, Borivali, Mumbai Suburban,… Greater Mumbai (M Corp.), Mumbai Suburban | Power | 8 acres | Coastal clearance granted | 11 Mar 2024 |
| Proposed Power Supply to Global Vipasana Pagoda, Gorai, Mumbai Greater Mumbai (M Corp.), Mumbai Suburban | Power | 1.2 acres | Coastal clearance granted | 19 Oct 2023 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| 400 kV Tata Power Vikhroli-Dharavi Scheme at Vikhroli, Mumbai, Maharashtra by M/s. Tata… Greater Mumbai (M Corp.), Mumbai Suburban | Power | 6.1 acres | Initial checks | 4 Nov 2026 |
| 220kV/33kV EHV Sub-Station in Kandivali Greater Mumbai (M Corp.), Mumbai Suburban | Power | 403.6 acres | Lapsed | 22 Sept 2026 |
| Diversion of 1.6202 Ha. Forest (Mangrove) Land for Proposed Shifting of Transmission Lines Na, Mumbai Suburban | Power | 15.1 acres | More information requested | 20 Aug 2026 |
| 400 kV Tata Power Vikhroli-Dharavi Scheme at Vikhroli, Mumbai, Maharashtra by M/s. Tata… Greater Mumbai (M Corp.), Mumbai Suburban | Power | 4.6 acres | Under coastal review | 18 Jul 2026 |
| Diversion of Forest Land for Proposed Shifting of Transmission Lines at Mandale &… Greater Mumbai (M Corp.), Mumbai Suburban | Power | 0.9 acres | Lapsed | 26 Nov 2025 |
| Retaining wall at boundary of Pandit Deen Dayal Upadhyay Garden Near Windermere CHS CTS… Greater Mumbai (M Corp.), Mumbai Suburban | Power | 0.2 acres | Recommended by coastal authority | 16 Jul 2025 |
| Diversion of Mangrove Forest land for laying 33KV Multi Transmission Line Project,… Greater Mumbai (M Corp.), Mumbai Suburban | Power | 4.5 acres | More information requested | 26 Jun 2025 |
| Diversion of forest land for 33 KV Multi Circuit Transmission Line crossing Gorai Creek Greater Mumbai (M Corp.), Mumbai Suburban | Power | 8 acres | Lapsed | 27 May 2024 |
| 33 KV Multi Circuit Transmission Tower line at Gorai, Borivali, Mumbai Suburban,… Greater Mumbai (M Corp.), Mumbai Suburban | Power | 8 acres | Coastal clearance granted | 11 Mar 2024 |
| Proposed Power Supply to Global Vipasana Pagoda, Gorai, Mumbai Greater Mumbai (M Corp.), Mumbai Suburban | Power | 1.2 acres | Coastal clearance granted | 19 Oct 2023 |
| Proposed Power Supply to Global Vipasana Pagoda, Gorai, Mumbai Greater Mumbai (M Corp.), Mumbai Suburban | Power | 1.2 acres | Lapsed | 19 Oct 2023 |
Questions people ask
How many power projects are planned in Mumbai Suburban?
11 power projects in Mumbai Suburban have applied for approval since January 2022. 7 of them are active (not withdrawn, lapsed or rejected) and 4 are still awaiting a decision.
What was approved most recently in Mumbai Suburban?
Retaining wall at boundary of Pandit Deen Dayal Upadhyay Garden Near Windermere CHS CTS No. 1A/3B abutting along the Oshiwara River at Andheri (West) in K/W Ward in Greater Mumbai (M Corp.) — “Recommended by coastal authority” on 4 Sept 2025.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.
Most active developers in Mumbai Suburban
The Tata Power Co in Mumbai4
Brihanmumbai Municipal Corporation in Mumbai3- AEAdani Electricity Mumbai in Mumbai3