What is Developing? Open the mapMap

Power projects in Mayurbhanj, Odisha

2 power projects in Mayurbhanj district, Odisha, have applied for environmental, forest, wildlife or coastal approval since January 2022. 1 are still filed or under review, and 0 were filed in the last 30 days. Updated 27 Nov 2026.

Explore Mayurbhanj on the live map

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

2power projects
1filed or under review
0filed in the last 30 days

Where they are in the approval process

StatusProjects
Filed or under review1
Approved1

Recently filed

ProjectTypeSizeStatusFiled
Electrification of Chakidi GP's Unelectrified House Holds under BGJY ON GRID SCHEME
Chakidi, Bangiriposi
Power11.2 acresMore information requested17 Nov 2025
132KV Two Phase line from Rairangpur Grid Substation to 132KV RTSS Rairangpur under…
Badada, Rairangpur Town
Power218.9 acresForest land use approved8 Jan 2023

Questions people ask

How many power projects are planned in Mayurbhanj?

2 power projects in Mayurbhanj have applied for approval since January 2022. 2 of them are active (not withdrawn, lapsed or rejected) and 1 are still awaiting a decision.

What was approved most recently in Mayurbhanj?

132KV Two Phase line from Rairangpur Grid Substation to 132KV RTSS Rairangpur under Mayurbhanj District in Badada — “Forest land use approved” on 6 May 2026.

How often is this list updated?

Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.

Other districts in Odisha