Where they are in the approval process
| Status | Projects |
|---|---|
| Approved | 1 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Neemrana-II-Kotputli 400 kV D/c line (Quad) and LILO of both ckts. of 400 kV Gurugram… Kharkheri, Taoru | Power | 16,622 acres | Forest land use approved | 18 Jul 2024 |
Questions people ask
How many power projects are planned in Nuh?
1 power projects in Nuh have applied for approval since January 2022. 1 of them are active (not withdrawn, lapsed or rejected) and 0 are still awaiting a decision.
What was approved most recently in Nuh?
Neemrana-II-Kotputli 400 kV D/c line (Quad) and LILO of both ckts. of 400 kV Gurugram (PG) – Sohna Road (GPTL) D/c line (Quad) at Neemrana-II S/s Transmission line in Kharkheri — “Forest land use approved” on 13 Apr 2026.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.