7power projects
4filed or under review
0filed in the last 30 days

Where they are in the approval process

StatusProjects
Filed or under review2
In-principle approval2
Approved1
Withdrawn or lapsed2

Recently filed

ProjectTypeSizeStatusFiled
Laying of Electrical Cable 33 kv U/G XLPE cables by Pashchimanchal Vidyut Vitran Nigam…
Rithani, Meerut
Power₹1.8 croreIn-principle approval, conditions pending29 Jun 2026
Expansion of Captive Power Plant from 8 MW to 12.5 MW of M/s Dev Priya Products Private…
Muzaffarnagar Saini, Meerut
Power20.2 acresUnder environmental review8 Jun 2026
Proposed Protected Forest Land To Be Diverted For Laying of Proposed 33KV Underground…
Kapsadh, Sardhana
Power1.5 acresLapsed11 May 2026
Lilo of 220 KV D/C Nara-Jansath @ 765 KV S/S Meerut Transmission Line
Nasarpur, Mawana
Power2,169.4 acresForest land use approved16 Jan 2024
220 KV D/C Meerut(765)- Mawana Line
Gabari, Mawana
Power485.3 acresIn-principle approval, conditions pending24 Oct 2023
11 KV HT line to 33/11 KV Sub station Naglapatu of DFCCIL
Nagla Patu, Meerut
Power3 acresLapsed14 Feb 2023
11 KV HT line for New Sakoti Crossing Station of DFCCIL
Jasratpur, Sardhana
Power0.5 acresMore information requested25 Jan 2023

Questions people ask

How many power projects are planned in Meerut?

7 power projects in Meerut have applied for approval since January 2022. 5 of them are active (not withdrawn, lapsed or rejected) and 4 are still awaiting a decision.

What was approved most recently in Meerut?

Lilo of 220 KV D/C Nara-Jansath @ 765 KV S/S Meerut Transmission Line in Nasarpur — “Forest land use approved” on 17 Mar 2026.