Quick answers
What is this project?
Expansion of existing Membrane Cell based Caustic Soda (from 400 TPD to 1000 TPD), Chlorine Derivative Chemicals (from 350 TPD to 720 TPD) and installation of Membrane Cell based Caustic Potash Plant (100 TPD), Chloromethanes (150 TPD), Carbon tetrachloride (70 TPD), Chlorofluorocarbons (50 TPD) within the existing plant premises is a lapsed industrial project in Balabhadrapuram, Biccavolu, East Godavari, Andhra Pradesh. The site covers 246.5 acres.
Who is building it?
The applicant is Quixo Technologies Private Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Balabhadrapuram, Biccavolu, East Godavari, Andhra Pradesh.
How big is it?
It has a stated cost of ₹2,450 crore and a site of 246.5 acres.
When was it filed?
The application was filed on 4 Nov 2023.
Project details
| Official title | Expansion of existing Membrane Cell based Caustic Soda (from 400 TPD to 1000 TPD), Chlorine Derivative Chemicals (from 350 TPD to 720 TPD) and installation of Membrane Cell based Caustic Potash Plant (100 TPD), Chloromethanes (150 TPD), Carbon tetrachloride (70 TPD), Chlorofluorocarbons (50 TPD) within the existing plant premises at Village: Balabhadhrapuram, Mandal: Biccavolu & at Village: G.Dontamuru (V), Mandal: Rangampeta, District: East Godavari (Andhra Pradesh) |
|---|---|
| Status | Lapsed |
| Status since | 29 Oct 2024 |
| Application filed | 4 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Quixo Technologies Private Limited |
| Land area | 246.5 acres (99.7 ha) |
| Project cost | ₹2,450 crore |
| Village / locality | Balabhadrapuram |
| Taluk / tehsil | Biccavolu |
| District | East Godavari |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-00512 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Early planning filed 4 Nov 2023 (this page) | Lapsed | 246.5 acres | ₹2,450 crore |
| Expansion filed 26 Oct 2023 | Lapsed | 246.5 acres | ₹2,450 crore |
In context
17 applications in East Godavari since January 2022 are in the same category (Industry): 8 approved, 5 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 38 days from filing to approval. At 246.5 acres, this one is larger than 82% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Balabhadrapuram, Biccavolu, East Godavari, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of existing Membrane Cell based Caustic Soda (from 400 TPD to 1000… — environmental approval granted, 0 m away
- Expansion of existing Membrane Cell based Caustic Soda (from 400 TPD to 1000… — lapsed, 0 m away
- M/s Sri Devi Minerals, Mining of Gravel over an extent of 1.416 Hect — environmental approval granted, 600 m away
- Mining project by M/s Chandramouli Earth Movers, Mg.P: Sri K Satti Babu — environmental approval granted, 1.2 km away
- Mining project by M/s Meenaakshi Minerals — environmental approval granted, 1.2 km away
- Mining project by M/s. Sri Shiva Shakthi Agencies — environmental approval granted, 2.3 km away
- Project by M/s. K.P.R Cropsciences Pvt Ltd — initial checks, 3.3 km away
- Transfer of EC of M/s. K.P.R Agrochem Ltd to M/s. K.P.R Cropsciences Pvt Ltd… — environmental approval granted, 3.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.