Quick answers
What is Kumar Minerals - 14.955 Ha (Quartz Mine)?
Kumar Minerals - 14.955 Ha (Quartz Mine) is an approved mining project in Peddannavaripalle, Talupula, Sri Sathya Sai, Andhra Pradesh. The site covers 37 acres.
Who is building it?
The applicant is Kumar Minerals.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 6 Jan 2026), as of 27 Nov 2026.
Where is it?
In Peddannavaripalle, Talupula, Sri Sathya Sai, Andhra Pradesh.
How big is it?
It has a stated cost of ₹80 lakh and a site of 37 acres.
When was it filed?
The application was filed on 22 Nov 2025.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 6 Jan 2026 |
| Application filed | 22 Nov 2025 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Mining |
| Applicant | Kumar Minerals |
| Land area | 37 acres (15 ha) |
| Project cost | ₹80 lakh |
| Village / locality | Peddannavaripalle |
| Taluk / tehsil | Talupula |
| District | Sri Sathya Sai |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-02193 |
In context
123 applications in Sri Sathya Sai since January 2022 are in the same category (Mining): 88 approved, 7 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 37 acres, this one is larger than 92% of them.
No other mining lease on record is within 500 m of this site; 3 have applied within 5 km.
Where it is
Peddannavaripalle, Talupula, Sri Sathya Sai, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Quartz Mine Over an Extent of 14.955 Ha. — environmental approval granted, 0 m away
- Mining project by M/S. Nagavarshitha Mines and Minerals — more information requested, 750 m away
- Mining project by M/s. MY ROOF CONSTRUCTIONS — environmental approval granted, 1.3 km away
- Mining project by M/s. MY ROOF CONSTRUCTIONS — cleared for impact study, 1.3 km away
- Quartz Mine Over an Extent of 6.110 Ha — environmental approval granted, 2.1 km away
- Dgps Survey for Grant of Quarry Lease for Quartz in Compt No 157 in F/O M/S.… — lapsed, 6.1 km away
- Dgps Survey for Grant of Quarry Lease for Quartz in Compt No 159 & 160 in F/O… — lapsed, 6.1 km away
- Dgps Survey for Grant of Quarry Lease for Quartz in Compt No 158 in F/O M/S.… — lapsed, 6.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.