Expansion of Integrated Cement Plant Clinker from 3.3 to 7.1 MTPA, Cement from 3.5 MTPA to 8.5 MTPA, WHRB power plant from 20 MW to 45 MW & Captive Power Plant of 100 MW

Expansion of Integrated Cement Plant Clinker from 3.3 to 7.1 MTPA, Cement from 3.5 MTPA to 8.5 MTPA, WHRB power plant from 20 MW to 45 MW & Captive Power Plant of 100 MW is a withdrawn industrial project in Kesanupalle, Dachepalle, Palnadu, Andhra Pradesh. The site covers 350.2 acres. Its stated project cost is ₹2,573 crore. As of 27 Nov 2026, its status is “Withdrawn” (since 25 Aug 2025).

See it on the live map All projects in Palnadu

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusWithdrawn
Status since25 Aug 2025
Application filed25 Aug 2025
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantChettinad Cement Corporation Private Limited
Land area350.2 acres (141.7 ha)
Project cost₹2,573 crore
Village / localityKesanupalle
Taluk / tehsilDachepalle
DistrictPalnadu
StateAndhra Pradesh
Location fromSite boundary on record
Our referenceWID-AP-02463

In context

17 applications in Palnadu since January 2022 are in the same category (Industry): 7 approved, 4 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 350.2 acres, this one is larger than 82% of them.

11 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Kesanupalle, Dachepalle, Palnadu, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Chettinad Cement Corporation Private Limited in Palnadu

4 Chettinad Cement Corporation projects in Palnadu
All 22 Chettinad Cement Corporation projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.