One of 4 filings for this project. The project's main page, with every filing and where each stands: Sri Vallabhaneni Venkateswara Rao
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 28 Sept 2025 |
| Application filed | 12 Aug 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Sri Vallabhaneni Venkateswara Rao |
| Land area | 12.4 acres (5 ha) |
| Project cost | ₹1 crore |
| Village / locality | Paritala |
| Taluk / tehsil | Kanchikacherla |
| District | Ntr |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-03027 |
All filings for this project
This project has 4 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 1 Jun 2026 | Environmental approval granted | 7.9 acres | ₹68 lakh |
| New project filed 1 Jun 2026 | Environmental approval granted | 12.4 acres | ₹1 crore |
| Early planning filed 12 Aug 2025 (this page) | Cleared for impact study | 12.4 acres | ₹1 crore |
| Early planning filed 12 Aug 2025 | Cleared for impact study | 7.9 acres | ₹68 lakh |
In context
243 applications in Ntr since January 2022 are in the same category (Mining): 182 approved, 31 filed or under review, and 30 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 12.4 acres, this one is larger than 75% of them.
7 other mining leases have applied within 500 m of this site; together with this one they cover 91.5 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 67 mining leases have applied within 5 km.
Where it is
Paritala, Kanchikacherla, Ntr, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sri Vallabhaneni Venkateswara Rao — environmental approval granted, 0 m away
- Sri Challagundla Harish Kumar — environmental approval granted, 200 m away
- Sri Challagundla Harish Kumar — cleared for impact study, 200 m away
- Sri R. Madhusudhan Rao — environmental approval granted, 250 m away
- Sri R. Madhusudhan Rao — cleared for impact study, 250 m away
- Mining project by M/s Sri Vijaya Lakshmi Stone Crusher (2.023 Ha.,) — cleared for impact study, 300 m away
- M/s Sri Kanaka Durga Mining Private Limited — environmental approval granted, 300 m away
- M/s Sri Kanaka Durga Mining Private Limited — cleared for impact study, 300 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.