Quick answers
What is Munikudali Sand Reach?
Munikudali Sand Reach is a proposed mining project in Munikudali, Seethanagaram, East Godavari, Andhra Pradesh. The site covers 70.4 acres.
Who is building it?
The applicant is Dubba Phani Bhushan Reddy.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Munikudali, Seethanagaram, East Godavari, Andhra Pradesh.
How big is it?
It has a stated cost of ₹25 lakh and a site of 70.4 acres.
When was it filed?
The application was filed on 7 Oct 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 18 Nov 2026 |
| Application filed | 7 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | Validity extension |
| Sector | Mining |
| Applicant | Dubba Phani Bhushan Reddy |
| Land area | 70.4 acres (28.5 ha) |
| Project cost | ₹25 lakh |
| Village / locality | Munikudali |
| Taluk / tehsil | Seethanagaram |
| District | East Godavari |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-03451 |
In context
252 applications in East Godavari since January 2022 are in the same category (Mining): 206 approved, 32 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 43 days from filing to approval. At 70.4 acres, this one is larger than 88% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 159.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 58 mining leases have applied within 5 km.
Where it is
Munikudali, Seethanagaram, East Godavari, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Munikudali Sand Reach — environmental approval granted, 0 m away
- Pendyala Sand Reach — environmental approval granted, 0 m away
- Munikudali Sand Reach — cleared for impact study, 0 m away
- Pendyala Sand Reach — cleared for impact study, 0 m away
- De-Casting of Sand in Prakkilanka Lankalu Block-13 over an extent of 2.39 Ha /… — environmental approval granted, 300 m away
- De-Casting of Sand in Prakkilanka Lankalu Block-13 over an extent of 2.39 Ha /… — cleared for impact study, 300 m away
- De-Casting of Sand in Prakkilanka Lankalu Block-14 over an extent of 5.07… — environmental approval granted, 350 m away
- De-Casting of Sand in Prakkilanka Lankalu Block-14 over an extent of 5.07… — cleared for impact study, 350 m away
More from Dubba Phani Bhushan Reddy in East Godavari
- De-Casting of Sand in Prakkilanka Lankalu Block-24 over an extent of 2.444 Ha.… — under environmental review
- De-Casting of Sand in Prakkilanka Lankalu Block-17 over an extent of 5.82 Ha.… — under environmental review
- De-Casting of Sand in Prakkilanka Lankalu Block-29 over an extent of 5.188 Ha.… — under environmental review
- De-Casting of Sand in Prakkilanka Lankalu Block-20 over an extent of 2.865 Ha… — under environmental review
- De-Casting of Sand in Prakkilanka Lankalu Block-10 over an extent of 23.35 Ha.… — under environmental review
- De-Casting of Sand in Prakkilanka Lankalu Block-21 over an extent of 2.913 Ha.… — under environmental review
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.