Environmental approval grantedIndustry · Anakapalli, Andhra Pradesh

Amendment of EC J-11011/813/2007-IA II(1) dated 16th Oct-2008,26th Sept 2012 and 22nd March 2013 and 16th Dec-2024 and 8th July-2025 Pioneer Aluminium Industries Limited , Andhra Pradesh, Alumina Refinery (1.5MTPA & Smelter 2,50,000TPA and CGPP150MW) calcination units pollution control equipment change from ESP to Bag filters to reduce particulate matter to bare minimum levels

Amendment of EC J-11011/813/2007-IA II(1) dated 16th Oct-2008,26th Sept 2012 and 22nd March 2013 and 16th Dec-2024 and 8th July-2025 Pioneer Aluminium Industries Limited , Andhra Pradesh, Alumina Refinery (1.5MTPA & Smelter 2,50,000TPA and CGPP150MW) calcination units pollution control equipment change from ESP to Bag filters to reduce particulate matter to bare minimum levels is an approved industrial project in Koduru, Makavarapalem, Anakapalli, Andhra Pradesh. The site covers 1,926 acres. As of 27 Nov 2026, its status is “Environmental approval granted” (since 4 Nov 2026).

See it on the live map All projects in Anakapalli

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusEnvironmental approval granted
Status since4 Nov 2026
Application filed4 Sept 2026
Approval soughtEnvironmental approval
Application typeAmendment
SectorIndustry
ApplicantPioneer Aluminium Industries Limited
Land area1,926 acres (779.4 ha)
Village / localityKoduru
Taluk / tehsilMakavarapalem
DistrictAnakapalli
StateAndhra Pradesh
Location fromSite boundary on record
Our referenceWID-AP-03514

What the filings say

What is planned

Pioneer Aluminium Industries Limited (formerly Anrak Aluminium Limited) has set up an integrated aluminium plant. The project includes an alumina refinery with a capacity of 1.5 million tonnes per annum (MTPA), an aluminium smelter of 0.25 MTPA, and a 150 MW captive power plant. The construction of the project was completed in March 2013 with an investment of ₹5,600 crore.

The applicant sought an amendment to use fuel oil as a regular fuel for the calciner in the alumina refinery, in addition to natural gas. Originally, natural gas was to be the primary fuel, with fuel oil as an alternate or emergency fuel. However, the Andhra Pradesh Government has not made Godavari gas available for the project. The calciner installed in the plant was designed for fuel oil, natural gas, and/or mixed fuel firing. The calciner chimneys have been designed for the sulphur content of fuel oil, with the original stack height increased from 60 m to 102.7 m to comply with this. The use of fuel oil is proposed until natural gas is made available by the Andhra Pradesh Gas Distribution Corporation (APGDC).

Layout and design

The plant is located near Rachapalle village, Makavarapalem Mandal, Anakapalli district, Andhra Pradesh. The layout plan shows a raw water pond, process water pond, red mud pond, smelter, refinery, power plant, and a township.

Land and surroundings

The nearest village, Rachapalle, is 0.20 km away. State Highway is 4 km away, and National Highway NH-5 is 8.6 km away. The Sarpanadi seasonal stream is 0.7 km from the plant site. The South Central railway line connecting Chennai and Howrah is 9 km away, with the nearest railway station at Bayyavaram. There are no national parks or sanctuaries within a 10 km radius. However, several reserved forests are located within this radius, including Panduru RF (2.7 km), Peddapalli RF (4.0 km), Gobburu RF (5.8 km), Payakarao peta RF (5.4 km), Tida RF (1.4 km), Guddepa RF (7.0 km), and Pangidi RF (7.0 km).

Water, power and access

The power and steam requirements of the alumina refinery will be met from the cogeneration plant, and that of the smelter will be initially met from the grid. A pithead coal-based power plant is planned to supply the power requirement for the aluminium smelter.

Environmental safeguards

The applicant proposes to develop a greenbelt over 190 hectares (more than 33% of the plant area) to act as a noise barrier and improve aesthetics. The plant is designed for zero discharge of process wastewater, which will be recycled. Red mud will be stored in a pond with an impervious lining to prevent groundwater contamination. Spent pot lining will be used in cement plants or disposed of in a secured landfill as per CPCB guidelines. Ash generated from the power plant will be entirely consumed by cement plants.

The applicant has taken steps to reduce pollution by not using pet coke in the power plant and by modifying air pollution control systems to reduce particulate matter emissions from 50 mg/Nm³ to 30 mg/Nm³. The calcination units will change pollution control equipment from electrostatic precipitators (ESP) to bag filters to reduce particulate matter to bare minimum levels. Continuous emission monitoring systems (CEMS) will be installed on the calciner stack to monitor PM, SO₂, and NOx levels, with real-time data shared with CPCB/SPCB.

Timeline

Amendment of EC J-11011/813/2007-IA II(1) Dated 16th Oct-2008,26th Sept 2012 and 22nd March 2013 and 16th Dec-2024 and 8th July-2025 Pioneer Aluminium Industries Limited , Andhra Pradesh, Alumina Refinery (1.5MTPA & Smelter 2,50,000TPA and CGPP150MW) Calcination Units Pollution Control Equipment Change from ESP to Bag Filters to Reduce Particulate Matter to Bare Minimum Levels site plan and layout

A drawing from the project's filings. Sign in free to see it.

Amendment of EC J-11011/813/2007-IA II(1) Dated 16th Oct-2008,26th Sept 2012 and 22nd March 2013 and 16th Dec-2024 and 8th July-2025 Pioneer Aluminium Industries Limited , Andhra Pradesh, Alumina Refinery (1.5MTPA & Smelter 2,50,000TPA and CGPP150MW) Calcination Units Pollution Control Equipment Change from ESP to Bag Filters to Reduce Particulate Matter to Bare Minimum Levels: Plot plan layout showing the refinery, smelter, power plant, ponds, and township (preview)🔒 Sign in free to see it
Plot plan layout showing the refinery, smelter, power plant, ponds, and township

In context

30 applications in Anakapalli since January 2022 are in the same category (Industry): 18 approved, 5 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1,926 acres, this one is larger than 63% of them.

6 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Koduru, Makavarapalem, Anakapalli, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Pioneer Aluminium Industries Limited in Anakapalli

All 4 Pioneer Aluminium Industries projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.