This proposed mining project by M/s Avenir Granites Mgptr: Sri Dodda Mahesh, Extent: 5.066 Hects., is in Govardhanapuram, Saravakota, Srikakulam, Andhra Pradesh. The site covers 12.5 acres.
Who is building it?
The applicant is Avenir Granites.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Govardhanapuram, Saravakota, Srikakulam, Andhra Pradesh.
How big is it?
It has a stated cost of ₹50 lakh and a site of 12.5 acres.
When was it filed?
The application was filed on 24 Oct 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 24 Oct 2026 |
| Application filed | 24 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Avenir Granites |
| Land area | 12.5 acres (5.1 ha) |
| Project cost | ₹50 lakh |
| Village / locality | Govardhanapuram |
| Taluk / tehsil | Saravakota |
| District | Srikakulam |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-03803 |
In context
286 applications in Srikakulam since January 2022 are in the same category (Mining): 209 approved, 37 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 12.5 acres, this one is larger than 78% of them.
5 other mining leases have applied within 500 m of this site; together with this one they cover 70.1 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 28 mining leases have applied within 5 km.
Where it is
Govardhanapuram, Saravakota, Srikakulam, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Mining project by M/s. Avenir Granites — under environmental review, 0 m away
- Sri Phanindra Kamepalli — under environmental review, 150 m away
- Mining project by M/s Avenir Granites — more information requested, 200 m away
- Mining project by M/s Avenir Granites — cleared for impact study, 200 m away
- Kum. Chinnala Syamala Saranya — under environmental review, 250 m away
- Quarry lease over an extent of 5.0 Ha held by M/s Mitra Granite, Managing… — environmental approval granted, 300 m away
- Quarry lease over an extent of 5.0 Ha held by M/s Mitra Granite, Managing… — not approved, 300 m away
- Mining project by M/s Avenir Granites — more information requested, 400 m away
More from Avenir Granites in Srikakulam
- Mining project by M/s. Avenir Granites — under environmental review
- Mining project by M/s. Avenir Granites — under environmental review
- M/ s Avenir Granites Mgptr: Sri Dodda Mahesh, Extent: 5.087 Hects., — under environmental review
- Mining project by M/s Avenir Granites — more information requested
- Mining project by M/s Avenir Granites — more information requested
- Mining project by M/s Avenir Granites — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.