One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Steel Plant – DRI Kilns (Sponge Iron from 33,000 TPA to 1,32,000 TPA), New…
Project details
| Official title | Expansion of Steel Plant – DRI Kilns (Sponge Iron from 33,000 TPA to 1,32,000 TPA), New Induction Furnaces along with CCM & LRF (Hot Billets/MS Billets/ Ingots)-3,96,000 TPA, Rolling Mill (TMT Bars/Structural Steel Strips/MS Pipes/ MS Tubes/Galvanized Pipes - 3,96,000 TPA (85 % Hot charging remaining 15% through RHF with LDO/Producer Gas as fuel), Coal Gasifier for Reheating Furnace – 3,500 Nm3/hr., WHRB based Power Plant - 8.0 MW, FBC based Power Plant - 4.0 MW, Brick Manufacturing unit - 13,0 |
|---|---|
| Status | Under environmental review |
| Status since | 5 Nov 2026 |
| Application filed | 27 Jan 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Hariom Pipe Industries Limited |
| Land area | 112.4 acres (45.5 ha) |
| Project cost | ₹530.9 crore |
| Village / locality | Hiradahalu |
| Taluk / tehsil | D.Hirehal |
| District | Anantpur |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-04087 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 27 Jan 2026 (this page) | Under environmental review | 112.4 acres | ₹530.9 crore |
| Early planning filed 3 Apr 2025 | Cleared for impact study | 112.4 acres | ₹530.9 crore |
In context
18 applications in Anantpur since January 2022 are in the same category (Industry): 11 approved, 3 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 112.4 acres, this one is smaller than 72% of them.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Hiradahalu, D.Hirehal, Anantpur, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 33,000 TPA to 1,32,000… — cleared for impact study, 0 m away
- Proposed expansion of Sponge Iron plant from 100 TPD to 1700 TPD &… — lapsed, 50 m away
- Expansion of Sponge Iron Manufacturing Plant from 1,00,000 MT per Annum to… — lapsed, 2 km away
- Mining of Road Metal & Building Stone and Gravel Mine over an extent of 2.796… — environmental approval granted, 2.9 km away
- Sri G. Raghavendra — environmental approval granted, 3.1 km away
- M/S B.B. Minerals, Mg.Part: Smt. N. Aruna (Extension of validity of EC) for… — environmental approval granted, 3.2 km away
- M/s Sai Balaji Minerals OBULAPURAM IRON ORE Mine(Violation) — lapsed, 4.5 km away
- G3 / G2 Level Prospecting for Iron Ore inMincheri RF Iron Ore Block of M/s… — forest land use approved, 4.5 km away
All 3 Hariom Pipe Industries projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.