Quick answers
What is this project?
Expansion of Grain based Distillery Plant from 200 KLPD (Ethanol) to 300 KLPD (200 Ethanol & 100 KLPD RS/ENA/Ethanol) and 6.2 MW Cogeneration Power Plant by M/s. Assago Industries Private Limited is a proposed industrial project in Gummalladuddi, Gokavaram, East Godavari, Andhra Pradesh. The site covers 24.9 acres.
Who is building it?
The applicant is Assago Industries Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Gummalladuddi, Gokavaram, East Godavari, Andhra Pradesh.
How big is it?
It has a stated cost of ₹423.6 crore and a site of 24.9 acres.
When was it filed?
The application was filed on 16 Oct 2026.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Grain based Distillery Plant from 200 KLPD (Ethanol) to 300 KLPD (200…
Project details
| Official title | Expansion of Grain based Distillery Plant from 200 KLPD (Ethanol) to 300 KLPD (200 Ethanol & 100 KLPD RS/ENA/Ethanol) and 6.2 MW Cogeneration Power Plant at Village Gummalladoddi, Tehsil Gokavaram, District East Godavari, Andhra Pradesh by M/s. Assago Industries Private Limited |
|---|---|
| Status | More information requested |
| Status since | 30 Oct 2026 |
| Application filed | 16 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Assago Industries Private Limited |
| Land area | 24.9 acres (10.1 ha) |
| Project cost | ₹423.6 crore |
| Village / locality | Gummalladuddi |
| Taluk / tehsil | Gokavaram |
| District | East Godavari |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-04096 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 16 Oct 2026 (this page) | More information requested | 24.9 acres | ₹423.6 crore |
| Early planning filed 11 Aug 2025 | Cleared for impact study | 24.9 acres | ₹423.6 crore |
In context
17 applications in East Godavari since January 2022 are in the same category (Industry): 8 approved, 5 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 38 days from filing to approval. At 24.9 acres, this one is smaller than 71% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Gummalladuddi, Gokavaram, East Godavari, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Grain based Distillery Plant from 200 KLPD (Ethanol) to 300 KLPD… — cleared for impact study, 0 m away
- Sri T.Venkateswara Rao — environmental approval granted, 2.4 km away
- Sri DVVSS Subrahmanyam Raju, Extent: 2.600 Hects., — initial checks, 5.2 km away
- Sri Padala Satyanarayana Reddy, Extent: 4.961 Hects., — initial checks, 5.3 km away
- Sri Reddy Naga Malleswara Rao, 3.998 Hects., — under environmental review, 6.6 km away
- Pidugu Jogeswara Rao, Extent: 3.962 Hects — initial checks, 6.8 km away
- Diversion of 0.070 ha of Forest Land and 0.08 ha in Non-Forest Land for laying… — initial checks, 7.4 km away
- Diversion of 0.070 ha of Forest Land and 0.08 ha in Non-Forest Land for laying… — more information requested, 7.4 km away
About this information