Quick answers
What is this project?
MANUFACTURING OF 93352 MTPA of SUSTAINABLE AVIATION FUEL (93,000 MTPA) AND BIOFUEL (352 MTPA) BY M/S SAFONE INDIA SPKOMPACT PRIVATE LIMITED - EC + CRZ CLEARANCE is a proposed industrial project in Ganganapalli, Kakinada (Rural), Kakinada, Andhra Pradesh. The site covers 114.3 acres.
Who is building it?
The applicant is Safone India Spkompact Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 4 Sept 2026), as of 27 Nov 2026.
Where is it?
In Ganganapalli, Kakinada (Rural), Kakinada, Andhra Pradesh.
How big is it?
It has a stated cost of ₹2,500 crore and a site of 114.3 acres.
When was it filed?
The application was filed on 2 Jul 2026.
Project details
| Official title | PROPOSAL FOR MANUFACTURING OF 93352 MTPA of SUSTAINABLE AVIATION FUEL (93,000 MTPA) AND BIOFUEL (352 MTPA) BY M/S SAFONE INDIA SPKOMPACT PRIVATE LIMITED - EC + CRZ CLEARANCE |
|---|---|
| Status | Cleared for impact study |
| Status since | 4 Sept 2026 |
| Application filed | 2 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Safone India Spkompact Private Limited |
| Land area | 114.3 acres (46.3 ha) |
| Project cost | ₹2,500 crore |
| Village / locality | Ganganapalli |
| Taluk / tehsil | Kakinada (Rural) |
| District | Kakinada |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-04136 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 16 Sept 2026 | Under coastal review | ₹3 lakh | |
| Early planning filed 2 Jul 2026 (this page) | Cleared for impact study | 114.3 acres | ₹2,500 crore |
In context
26 applications in Kakinada since January 2022 are in the same category (Industry): 13 approved, 6 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 114.3 acres, this one is smaller than 85% of them.
24 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ganganapalli, Kakinada (Rural), Kakinada, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- MANUFACTURING OF 93352 MTPA of SUSTAINABLE AVIATION FUEL (93,000 MTPA) AND… — under coastal review, 0 m away
- Transfer of Environmental clearance (EC) from M/s Godavari Fertilisers and… — environmental approval granted, 200 m away
- Transfer of Environmental clearance (EC) from Coromandel Fertilisers Ltd to… — environmental approval granted, 200 m away
- "proposed Product Mix for Production of Tmap/Tdap/Tmkp Through… — initial checks, 200 m away
- Proposed Product Mix for Production of Tmap/Tdap/Tmkp Through Re-Configuration… — initial checks, 200 m away
- Proposed Product Mix for Production of Tmap/Tdap/Tmkp Through Re-Configuration… — initial checks, 200 m away
- Expansion of Fertilizer Plants in Coromandel Kakinada Plant at Vakalapudi (V),… — environmental approval granted, 200 m away
- Amalgamation of Environmental Clearances and Amendment/Expansion of Fertilizer… — environmental approval granted, 400 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.