What is Developing? Open the mapMap

WithdrawnMining · West Karbi Anglong, Assam

Kapili River Sand Mining Permit Area (Plot-2)

Kapili River Sand Mining Permit Area (Plot-2) is a withdrawn mining project in Amring R.F, Donka, West Karbi Anglong, Assam. The site covers 11.4 acres. Its stated project cost is ₹1.4 crore. As of 27 Nov 2026, its status is “Withdrawn” (since 22 Aug 2025).

See it on the live map All projects in West Karbi Anglong

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is Kapili River Sand Mining Permit Area (Plot-2)?

Kapili River Sand Mining Permit Area (Plot-2) is a withdrawn mining project in Amring R.F, Donka, West Karbi Anglong, Assam. The site covers 11.4 acres.

Who is building it?

The applicant is Sumod Naiding.

Has it been approved?

No. The application was withdrawn on 22 Aug 2025, so it is no longer under consideration.

Where is it?

In Amring R.F, Donka, West Karbi Anglong, Assam.

How big is it?

It has a stated cost of ₹1.4 crore and a site of 11.4 acres.

When was it filed?

The application was filed on 22 Aug 2025.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Kapili River Sand Mining Permit Area (Plot-2)

Project details

StatusWithdrawn
Status since22 Aug 2025
Application filed22 Aug 2025
Approval soughtEnvironmental approval
Application typeNew project
SectorMining
ApplicantSumod Naiding
Land area11.4 acres (4.6 ha)
Project cost₹1.4 crore
Village / localityAmring R.F
Taluk / tehsilDonka
DistrictWest Karbi Anglong
StateAssam
Location fromSite boundary on record
Our referenceWID-AS-01404

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Ownership transfer filed 16 Mar 2026Environmental approval granted11.4 acres₹74 lakh
New project filed 22 Aug 2025 (this page)Withdrawn11.4 acres₹1.4 crore

In context

29 applications in West Karbi Anglong since January 2022 are in the same category (Mining): 10 approved, 6 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 11.4 acres, this one is larger than 83% of them.

No other mining lease on record is within 500 m of this site; 2 have applied within 5 km.

Where it is

Amring R.F, Donka, West Karbi Anglong, Assam. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.