Project details
| Status | Not approved |
|---|---|
| Status since | 6 Mar 2025 |
| Application filed | 6 Mar 2025 |
| Approval sought | Environmental approval |
| Application type | Validity extension |
| Sector | Mining |
| Applicant | Mridul Boro |
| Land area | 1,000 m² |
| Project cost | ₹30 lakh |
| Village / locality | Tegheriagaon No2 |
| Taluk / tehsil | Sonapur |
| District | Kamrup Metropolitan |
| State | Assam |
| Location from | Site boundary on record |
| Our reference | WID-AS-01469 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Validity extension filed 6 Mar 2025 (this page) | Not approved | 0.2 acres | ₹30 lakh |
| New project filed 23 May 2023 | Environmental approval granted | 0.2 acres | ₹30 lakh |
In context
82 applications in Kamrup Metropolitan since January 2022 are in the same category (Mining): 61 approved, 3 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 0.2 acres, this one is smaller than 90% of them.
2 other mining leases have applied within 500 m of this site; together with this one they cover 1.6 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 10 mining leases have applied within 5 km.
Where it is
Tegheriagaon No2, Sonapur, Kamrup Metropolitan, Assam. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 1 No Tegheria Village Ordinary Earth Mining Permit Area — environmental approval granted, 0 m away
- 1 No. Tegheria P.P. Land Ordinary Earth Mining Permit Area — environmental approval granted, 100 m away
- 1 No. Tegheria P.P. Land Ordinary Earth Mining Permit Area — lapsed, 100 m away
- 1 No. Tegheria P.P. Land Ordinary Earth Mining Permit Area — environmental approval granted, 100 m away
- Tetelia Village Ordinary Earth Mining Permit Area — environmental approval granted, 450 m away
- Helagog Govt. Land Ordinary Earth Mining Permit Area — environmental approval granted, 600 m away
- 2 No. Tegeria Earth Mining Permit Area — environmental approval granted, 750 m away
- Helagog Govt. Land Stone Mining Permit Area — environmental approval granted, 800 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.