Under environmental reviewMining · Rohtas, Bihar

Kalyanpur Cement Limestone Mine [Total Area-40.45 ha, (Existing Cement Plant, Limestone Crusher, Colony–29.14 Ha, EC available); Remaining area–11.31 Ha for Mining] with Limestone Production (including mineral rejects)-0.5 Million TPA, Soil-0.38 Million TPA & OB-0.90 Million TPA (Tot. Excavation-1.78 Million TPA) alongwith Crusher of 250 TPH, handling legacy waste/mineral reject/OB waste–0.9 MTPA

Kalyanpur Cement Limestone Mine [Total Area-40.45 ha, (Existing Cement Plant, Limestone Crusher, Colony–29.14 Ha, EC available); Remaining area–11.31 Ha for Mining] with Limestone Production (including mineral rejects)-0.5 Million TPA, Soil-0.38 Million TPA & OB-0.90 Million TPA (Tot. Excavation-1.78 Million TPA) alongwith Crusher of 250 TPH, handling legacy waste/mineral reject/OB waste–0.9 MTPA is a proposed mining project in Kalyanpur, Rohtas, Bihar. The site covers 202.4 acres. Its stated project cost is ₹15.8 crore. As of 27 Nov 2026, its status is “Under environmental review” (since 29 Oct 2026).

See it on the live map All projects in Rohtas

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleKalyanpur Cement Limestone Mine [Total Area-40.45 ha, (Existing Cement Plant, Limestone Crusher, Colony–29.14 Ha, EC available); Remaining area–11.31 Ha for Mining] with Limestone Production (including mineral rejects)-0.5 Million TPA, Soil-0.38 Million TPA & OB-0.90 Million TPA (Tot. Excavation-1.78 Million TPA) alongwith Crusher of 250 TPH, handling legacy waste/mineral reject/OB waste–0.9 MTPA located at Village Kalyanpur, Taluka Rohtas, District Rohtas, Bihar by Dalmia Cement (Bharat) Ltd.
StatusUnder environmental review
Status since29 Oct 2026
Application filed23 Oct 2026
Approval soughtEnvironmental approval
Application typeEarly planning
SectorMining
ApplicantDalmia Cement (Bharat) Limited
Land area202.4 acres (81.9 ha)
Project cost₹15.8 crore
Village / localityKalyanpur
Taluk / tehsilRohtas
DistrictRohtas
StateBihar
Location fromSite boundary on record
Our referenceWID-BR-01650

In context

78 applications in Rohtas since January 2022 are in the same category (Mining): 60 approved, 12 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 36 days from filing to approval. At 202.4 acres, this one is larger than 65% of them.

No other mining lease on record is within 500 m of this site; 4 have applied within 5 km.

Where it is

Kalyanpur, Rohtas, Bihar. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Dalmia Cement (Bharat) Limited in Rohtas

9 Dalmia Cement (Bharat) projects in Rohtas
All 56 Dalmia Cement (Bharat) projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.