Quick answers
What is Madhota Limestone Quarry?
Madhota Limestone Quarry is a proposed mining project in Madhota, Bastar, Chhattisgarh. The site covers 5.9 acres.
Who is building it?
The applicant is Tatu Kashyap.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Madhota, Bastar, Chhattisgarh.
How big is it?
It has a stated cost of ₹30 lakh and a site of 5.9 acres.
When was it filed?
The application was filed on 8 Aug 2023.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 8 Aug 2023 |
| Application filed | 8 Aug 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Tatu Kashyap |
| Land area | 5.9 acres (2.4 ha) |
| Project cost | ₹30 lakh |
| Village / locality | Madhota |
| Taluk / tehsil | Bastar |
| District | Bastar |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00769 |
In context
180 applications in Bastar since January 2022 are in the same category (Mining): 35 approved, 23 filed or under review, and 122 withdrawn, lapsed or rejected. The approved ones took a median of 8 months from filing to approval. At 5.9 acres, this one is larger than 82% of them.
No other mining lease on record is within 500 m of this site; 11 have applied within 5 km.
Where it is
Madhota, Bastar, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Madhota Limestone Quarry, Lessee- Shri Ram Gopal Netam, Area - 1.90 Ha. Khasra… — environmental approval granted, 2.2 km away
- Madhota Limestone Quarry, Lessee- Shri Ram Gopal Netam, Area - 1.90 Ha. Khasra… — not approved, 2.2 km away
- Madhota Limestone mine — under environmental review, 2.2 km away
- Faizan Ahmed Sheikh — initial checks, 3.2 km away
- Tikanpal Lime Stone Quarry — environmental approval granted, 4.3 km away
- Mining project by M/s Subhan Stone Crusher — environmental approval granted, 4.4 km away
- Tikanpal Limestone Mine — environmental approval granted, 4.4 km away
- Limestone Quarry, Area 0.90 ha, Village Tikanpal, project proponent shri… — not approved, 4.4 km away