Quick answers
What is Vivek Goyal?
Vivek Goyal is a rejected mining project in Changori, Lundra, Surguja, Chhattisgarh. The site covers 2.5 acres.
Who is building it?
The applicant is Vivek Goyal.
Has it been approved?
No. The application was rejected on 20 Dec 2025.
Where is it?
In Changori, Lundra, Surguja, Chhattisgarh.
How big is it?
It has a stated cost of ₹13 lakh and a site of 2.5 acres.
When was it filed?
The application was filed on 26 Jan 2024.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Vivek Goyal
Project details
| Status | Not approved |
|---|---|
| Status since | 20 Dec 2025 |
| Application filed | 26 Jan 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Vivek Goyal |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹13 lakh |
| Village / locality | Changori |
| Taluk / tehsil | Lundra |
| District | Surguja |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-01842 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Early planning filed 15 Jan 2025 | Cleared for impact study | 3 acres | ₹39 lakh |
| New project filed 16 Oct 2024 | Environmental approval granted | 2.5 acres | ₹13 lakh |
| Early planning filed 26 Jan 2024 (this page) | Not approved | 2.5 acres | ₹13 lakh |
In context
155 applications in Surguja since January 2022 are in the same category (Mining): 76 approved, 19 filed or under review, and 60 withdrawn, lapsed or rejected. The approved ones took a median of 7 months from filing to approval. At 2.5 acres, this one is smaller than 74% of them.
6 other mining leases have applied within 500 m of this site; together with this one they cover 30 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 35 mining leases have applied within 5 km.
Where it is
Changori, Lundra, Surguja, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Vivek Goyal — environmental approval granted, 0 m away
- Vivek Goyal — cleared for impact study, 150 m away
- Shri Manoj Kumar Yadav, Limestone Quarry, Village Changori, Area 2.848 Ha. — lapsed, 150 m away
- Limestone Quarry, Village Changori, Area 2.848 Ha, Project Proponent Shri… — cleared for impact study, 150 m away
- Limestone Quarry, Village Changori, Area 2.848 Ha Project Proponent Shri Manoj… — lapsed, 150 m away
- Manoj Kumar Agrawal — lapsed, 250 m away
- Manoj Kumar Agrawal — not approved, 250 m away
- Mohan Lal Agrawal — not approved, 300 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.