Environmental Clearance for Proposed "Expansion of AIIMS Hospital and Medical College" located at, Tatibandh, Raipur, C.G is a proposed building project in Raipur, Chhattisgarh. The site covers 63.8 acres.
Who is building it?
The applicant is Abhinav jaiswal.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹374.8 crore and a site of 63.8 acres.
When was it filed?
The application was filed on 19 Dec 2024.
Project details
| Status | More information requested |
|---|---|
| Status since | 16 Nov 2026 |
| Application filed | 19 Dec 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Buildings & townships |
| Applicant | Abhinav jaiswal |
| Land area | 63.8 acres (25.8 ha) |
| Project cost | ₹374.8 crore |
| Village / locality | Raipur |
| Taluk / tehsil | Raipur |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02092 |
In context
56 applications in Raipur since January 2022 are in the same category (Buildings & townships): 29 approved, 18 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 63.8 acres, this one is larger than 82% of them.
24 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Ramesh Steel Industries (Unit - II) — cleared for impact study, 1.4 km away
- Industrial project by Agrawal Round Rolling Mills Ltd. — cleared for impact study, 1.8 km away
- Regularization of Re-Rolling Mill plant of 30,000 MTPA capacity, in compliance… — cleared for impact study, 1.8 km away
- Regularization of Re-Rolling Mill plant of 30,000 TPA and Binding Wire/H.B.… — cleared for impact study, 1.8 km away
- Regularization of Re-Rolling Mill plant of 60,000 TPA and Fabrication of Tower… — cleared for impact study, 2.3 km away
- Proposed Residential cum Commercial complex project by Avinash Developers… — cleared for impact study, 2.6 km away
- Regularization of Coal Based Re-Rolling Mill plant of 8,000 MTPA capacity, in… — cleared for impact study, 2.8 km away
- Regularization of the existing manufacturing of Re-Rolled Products having… — more information requested, 2.8 km away