What is this project?
This lapsed mining project by M/s CG AGRO FARM (MANDIR HASAUD LIMESTONE QYARRY) LESSEE - VIPIN AGRAWAL, AREA - 2.01HA. KHASRA - 726/1, 2, 741, 742, 744 VILLAGE - MANDIR HASAUD TEH - AARANG DIST - RAIPUR (cg) is in Mandir Hasaud, Arang, Raipur, Chhattisgarh. The site covers 5 acres.
Who is building it?
The applicant is Vipin Agrawal.
Has it been approved?
No. The application was lapsed on 11 Jan 2026, so it is no longer under consideration.
Where is it?
In Mandir Hasaud, Arang, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹35 lakh and a site of 5 acres.
When was it filed?
The application was filed on 3 May 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 11 Jan 2026 |
| Application filed | 3 May 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Vipin Agrawal |
| Land area | 5 acres (2 ha) |
| Project cost | ₹35 lakh |
| Village / locality | Mandir Hasaud |
| Taluk / tehsil | Arang |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02104 |
In context
273 applications in Raipur since January 2022 are in the same category (Mining): 123 approved, 21 filed or under review, and 129 withdrawn, lapsed or rejected. The approved ones took a median of 11 months from filing to approval. At 5 acres, this one is larger than 53% of them.
10 other mining leases have applied within 500 m of this site; together with this one they cover 41.3 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 27 mining leases have applied within 5 km.
Where it is
Mandir Hasaud, Arang, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- M/s CG AGRO FARM (MANDIR HASAUD LIMESTONE QUARRY) LESSEE - VIPIN AGRAWAL, AREA… — cleared for impact study, 0 m away
- Mandirhasaud Limestone Quarry , Area - 1.035 ha., Shri Motumal Adwani — cleared for impact study, 250 m away
- Ramawtar Agrawal — lapsed, 300 m away
- Ram Avatar Agrawal — lapsed, 300 m away
- M/s MANDIR HASAUD LIMESTONE QUARRY ( SHRI KALYAN SINGH THAKUR) VILLAGE- MANDIR… — withdrawn, 350 m away
- Mandir Hasaud Limestone Quarry, Lessee - Shri Chandrahas Pandey Area - 0.785… — lapsed, 450 m away
- Mandir hasaud Limestone Quarry , Lease Area - 1.94 Acre (0.785 ha.) , Lessee -… — cleared for impact study, 450 m away
- Mining project by Mahi Builders and Developers — environmental approval granted, 450 m away
More from Vipin Agrawal in Raipur
- M/s CG AGRO FARM (MANDIR HASAUD LIMESTONE QUARRY) LESSEE - VIPIN AGRAWAL, AREA… — cleared for impact study
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.