Greenfield steel project consisting DRI plant to produce Sponge Iron 717500TPA, I/O Beneficiation1000000TPA, Pellet Plant600000TPA with PGP of 5x5500 Nm3/hr, MS Billets612500TPA Rerolled Steel Products582000TPA(through Hot Charging, RHF) SAF(2x9MVA+3x6MVA+3x4MVA) to produce SiMn96000TPA/FeMn120000TPA/FeSi52000TPA/Pig Iron192000TPA, Sinter Plant33000TPA, Coal Washery1000000TPA MS Pipe350000TPA, O2 Plant45000 Nm3/hr CPP-131MW(WHRB-56MW+FBC-75MW) Fly Ash Bricks 54900Brick/day, Slag crusher-350TPD

Greenfield steel project consisting DRI plant to produce Sponge Iron 717500TPA, I/O Beneficiation1000000TPA, Pellet Plant600000TPA with PGP of 5x5500 Nm3/hr, MS Billets612500TPA Rerolled Steel Products582000TPA(through Hot Charging, RHF) SAF(2x9MVA+3x6MVA+3x4MVA) to produce SiMn96000TPA/FeMn120000TPA/FeSi52000TPA/Pig Iron192000TPA, Sinter Plant33000TPA, Coal Washery1000000TPA MS Pipe350000TPA, O2 Plant45000 Nm3/hr CPP-131MW(WHRB-56MW+FBC-75MW) Fly Ash Bricks 54900Brick/day, Slag crusher-350TPD is a proposed industrial project in Kotmar, Raigarh, Chhattisgarh. The site covers 416.2 acres. Its stated project cost is ₹7.6 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 11 Dec 2024).

See it on the live map All projects in Raigarh

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Greenfield steel project consisting DRI plant to produce Sponge Iron 717500TPA, I/O Beneficiation1000000TPA, Pellet Plant600000TPA with PGP of 5x5500 Nm3/hr, MS Billets612500TPA Rerolled Steel Products582000TPA(through Hot Charging, RHF) SAF(2x9MVA+3x6MVA+3x4MVA) to produce SiMn96000TPA/FeMn120000TPA/FeSi52000TPA/Pig Iron192000TPA, Sinter Plant33000TPA, Coal Washery1000000TPA MS Pipe350000TPA, O2 Plant45000 Nm3/hr CPP-131MW(WHRB-56MW+FBC-75MW) Fly Ash Bricks 54900Brick/day, Slag crusher-350TPD is a proposed industrial project in Kotmar, Raigarh, Chhattisgarh. The site covers 416.2 acres.

Who is building it?

The applicant is Bpa Metallics Private Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 11 Dec 2024), as of 27 Nov 2026.

Where is it?

In Kotmar, Raigarh, Chhattisgarh.

How big is it?

It has a stated cost of ₹7.6 crore and a site of 416.2 acres.

When was it filed?

The application was filed on 2 Dec 2024.

Project details

StatusCleared for impact study
Status since11 Dec 2024
Application filed2 Dec 2024
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantBpa Metallics Private Limited
Land area416.2 acres (168.5 ha)
Project cost₹7.6 crore
Village / localityKotmar
Taluk / tehsilRaigarh
DistrictRaigarh
StateChhattisgarh
Location fromSite boundary on record
Our referenceWID-CG-02235

In context

113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 416.2 acres, this one is larger than 89% of them.

Where it is

Kotmar, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.