Quick answers
What is this project?
Expansion of Ferro Alloys Manufacturing Unit from 64,000 TPA to 88,000 TPA (Phase I: 76,000 TPA & Phase II: 88,000 TPA) (including 48,000 TPA of Medium & Low Carbon Ferro Alloys), Pig Iron (56,000 TPA) and Captive Power Plant from 20 MW to 28 MW (Phase I: 24 MW & Phase II: 28 MW) at Khasra No. 156, 500, 508, 509, 510, 511/1, 511/2,512/1,512/2, 513/1,-513/5 and Others, Urla Industrial Area, Raipur, Chhattisgarh is a proposed industrial project in Achholi, Raipur, Chhattisgarh. The site covers 43.5 acres.
Who is building it?
The applicant is Hira Power and Steels Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Achholi, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹247.4 crore and a site of 43.5 acres.
When was it filed?
The application was filed on 6 Oct 2025.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Ferro Alloys Manufacturing Unit from 64,000 TPA to 88,000 TPA (Phase I:…
Project details
| Status | Returned to applicant |
|---|---|
| Status since | 4 May 2026 |
| Application filed | 6 Oct 2025 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Hira Power and Steels Limited |
| Land area | 43.5 acres (17.6 ha) |
| Project cost | ₹247.4 crore |
| Village / locality | Achholi |
| Taluk / tehsil | Raipur |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02752 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 21 Dec 2025 | Environmental approval granted | 43.5 acres | ₹247.4 crore |
| Expansion filed 6 Oct 2025 (this page) | Returned to applicant | 43.5 acres | ₹247.4 crore |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 43.5 acres, this one is larger than 64% of them.
73 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Achholi, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Ferro Alloys Manufacturing Unit from 64,000 TPA to 88,000 TPA… — environmental approval granted, 0 m away
- Expansion of Ferro Alloys Manufacturing Unit from 64,000 TPA to 88,000 TPA… — lapsed, 0 m away
- Expansion of Manufacturing of Ferro Alloys from 48,000 TPA to 64,000 TPA — environmental approval granted, 0 m away
- Expansion of Ferro Alloys Production Unit (Unit II) located at Urla Industrial… — returned to applicant, 250 m away
- Expansion of Ferro Alloys Production Unit (Unit II) located at Urla Industrial… — returned to applicant, 250 m away
- Expansion of Ferro Alloys Production Unit (Unit II) located at Urla Industrial… — lapsed, 250 m away
- Expansion of Ferro Alloys Production Unit (Unit II) located at Urla Industrial… — environmental approval granted, 250 m away
- Expansion of Ferro Alloys Production Unit (Unit II) located at Urla Industrial… — cleared for impact study, 250 m away
More from Hira Power and Steels Limited in Raipur
- Expansion of Ferro Alloys Manufacturing Unit from 64,000 TPA to 88,000 TPA… — lapsed
- Expansion of Ferro Alloys Production Unit at P.H. No. 0028, Plot No.… — environmental approval granted
- Expansion of Ferro Alloys Production Unit at P.H. No. 0028, Plot No.… — cleared for impact study
- Expansion of Manufacturing of Ferro Alloys from 48,000 TPA to 64,000 TPA — environmental approval granted
6 Hira Power and Steels projects in Raipur
All 7 Hira Power and Steels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.