Greenfield steel plant comprising of DRI Kiln 1 x 350 TPD – 1,15,500 TPA, WHRB based Power Plant – 1 x 10 MW, FBC based Power Plant – 1 x 5 MW & Brick Manufacturing unit – 50,00,000 Bricks/Annum

Greenfield steel plant comprising of DRI Kiln 1 x 350 TPD – 1,15,500 TPA, WHRB based Power Plant – 1 x 10 MW, FBC based Power Plant – 1 x 5 MW & Brick Manufacturing unit – 50,00,000 Bricks/Annum is a proposed industrial project in Sakarra, Takhatpur, Bilaspur, Chhattisgarh. The site covers 120 acres. Its stated project cost is ₹190.7 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 14 Jul 2025).

See it on the live map All projects in Bilaspur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleEstablishment of Greenfield steel plant comprising of DRI Kiln 1 x 350 TPD – 1,15,500 TPA, WHRB based Power Plant – 1 x 10 MW, FBC based Power Plant – 1 x 5 MW & Brick Manufacturing unit – 50,00,000 Bricks/Annum
StatusCleared for impact study
Status since14 Jul 2025
Application filed4 Jun 2025
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantIMAEC Steel and Power Limited
Land area120 acres (48.6 ha)
Project cost₹190.7 crore
Village / localitySakarra
Taluk / tehsilTakhatpur
DistrictBilaspur
StateChhattisgarh
Location fromSite boundary on record
Our referenceWID-CG-02810

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 14 Mar 2026Returned to applicant120 acres₹190.7 crore
Early planning filed 4 Jun 2025 (this page)Cleared for impact study120 acres₹190.7 crore

In context

47 applications in Bilaspur since January 2022 are in the same category (Industry): 26 approved, 11 filed or under review, and 10 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 120 acres, this one is larger than 74% of them.

7 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Sakarra, Takhatpur, Bilaspur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.