| Official title | Establishment of Greenfield steel plant comprising of DRI Kiln 1 x 350 TPD – 1,15,500 TPA, WHRB based Power Plant – 1 x 10 MW, FBC based Power Plant – 1 x 5 MW & Brick Manufacturing unit – 50,00,000 Bricks/Annum |
|---|---|
| Status | Cleared for impact study |
| Status since | 14 Jul 2025 |
| Application filed | 4 Jun 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | IMAEC Steel and Power Limited |
| Land area | 120 acres (48.6 ha) |
| Project cost | ₹190.7 crore |
| Village / locality | Sakarra |
| Taluk / tehsil | Takhatpur |
| District | Bilaspur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02810 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 14 Mar 2026 | Returned to applicant | 120 acres | ₹190.7 crore |
| Early planning filed 4 Jun 2025 (this page) | Cleared for impact study | 120 acres | ₹190.7 crore |
In context
47 applications in Bilaspur since January 2022 are in the same category (Industry): 26 approved, 11 filed or under review, and 10 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 120 acres, this one is larger than 74% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sakarra, Takhatpur, Bilaspur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Greenfield steel plant comprising of DRI Kiln 1 x 350 TPD – 1,15,500 TPA, WHRB… — returned to applicant, 0 m away
- Kartik Ram Patel — environmental approval granted, 2.6 km away
- Itwa Brick Earthclay Quarry of Shobharam Ratre — environmental approval granted, 2.8 km away
- Hajarilal Bhardwaj — not approved, 2.8 km away
- Lalwani Brick Earth Quarry — environmental approval granted, 3.1 km away
- Harikripa Minerals Partner's Nidhi Rajpal & Kunal Rajpal — lapsed, 4.8 km away
- Harikripa Minerals Partner's Nidhi Rajpal & Kunal Rajpal — lapsed, 4.8 km away
- Mining project by M/s Harikripa Minerals, Partner Nidhi Rajpal & Kunal Rajpal — returned to applicant, 4.8 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.