Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 11 Jun 2026 |
| Application filed | 5 Feb 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Kamlesh Sahu |
| Land area | 4 acres (1.6 ha) |
| Project cost | ₹30 lakh |
| Village / locality | Khanda |
| Taluk / tehsil | Baikunthpur |
| District | Koriya |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02939 |
In context
83 applications in Koriya since January 2022 are in the same category (Mining): 37 approved, 18 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 7 months from filing to approval. At 4 acres, this one is smaller than 57% of them.
2 other mining leases have applied within 500 m of this site; together with this one they cover 9.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 8 mining leases have applied within 5 km.
Where it is
Khanda, Baikunthpur, Koriya, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Khada Brick Earthclay Quarry & Fix Chimney Brick Plant — cleared for impact study, 250 m away
- Khanda Brick Earthclay Quarry & Fixn Chimney Bricks Plant (Pro.- Devsharan… — environmental approval granted, 250 m away
- Soor Brick earth clay Quarry & fix chimney bricks plant , Area - 0.887 ha.… — initial checks, 650 m away
- Khada Bricks Earth Clay Quarry and Fix Cimney Bricks Plant Area - 1.80ha… — more information requested, 650 m away
- KHADA BRICKS EARTH CLAY QUARRY AND FIX CHIMNEY BRICKS PLANT AREA - 1.80HA.… — not approved, 650 m away
- Khodri and Khada Brics Earth Clay Quarry and Brikc Kiln Porject — environmental approval granted, 800 m away
- Khodri and Khada Brics Earth Clay Quarry and Brikc Kiln Porject — cleared for impact study, 800 m away
- Shiv Kumari — under environmental review, 1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.