Cleared for impact studyIndustry · Durg, Chhattisgarh

Greenfield steel plant comprising of DRI Kilns 2 x 350 TPD -2,31,000 TPA, Induction Furnaces with matching LRF & CCM (Hot Billets / Billets / Ingots) 4 x 20 T - 2,11,200 TPA, Rolling Mill (TMT bars / Structural Steel) (85% Hot charging with Hot Billets and remaining 15% through RHF with Producer gas as fuel – 1,98,000 TPA

Greenfield steel plant comprising of DRI Kilns 2 x 350 TPD -2,31,000 TPA, Induction Furnaces with matching LRF & CCM (Hot Billets / Billets / Ingots) 4 x 20 T - 2,11,200 TPA, Rolling Mill (TMT bars / Structural Steel) (85% Hot charging with Hot Billets and remaining 15% through RHF with Producer gas as fuel – 1,98,000 TPA is a proposed industrial project in Durg, Chhattisgarh. The site covers 214 acres. Its stated project cost is ₹365 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 19 Mar 2026).

See it on the live map All projects in Durg

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleEstablishment of Greenfield steel plant comprising of DRI Kilns 2 x 350 TPD -2,31,000 TPA, Induction Furnaces with matching LRF & CCM (Hot Billets / Billets / Ingots) 4 x 20 T - 2,11,200 TPA, Rolling Mill (TMT bars / Structural Steel) (85% Hot charging with Hot Billets and remaining 15% through RHF with Producer gas as fuel – 1,98,000 TPA, along with Coal gasifier for Reheating Furnace – 1 x 6,500 Nm3/hr, Submerged Electric Arc Furnace - 1 x 9 MVA (FeSi-7,000TPA / FeMn-20,000 TPA / SiMn-14
StatusCleared for impact study
Status since19 Mar 2026
Application filed9 Feb 2026
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantKeshav IRON
Land area214 acres (86.6 ha)
Project cost₹365 crore
Village / localityDurg
Taluk / tehsilDurg
DistrictDurg
StateChhattisgarh
Location fromSite boundary on record
Our referenceWID-CG-03512

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Early planning filed 9 Feb 2026 (this page)Cleared for impact study214 acres₹365 crore
Early planning filed 17 Nov 2025Returned to applicant269 acres₹365 crore

In context

41 applications in Durg since January 2022 are in the same category (Industry): 25 approved, 13 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 214 acres, this one is larger than 85% of them.

Where it is

Durg, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.