Shri Sunil Kumar Mishra,mohbhatta Dolomite Quarry Area 2.74hec is a proposed mining project in Mohbhata, Berla, Bametara, Chhattisgarh. The site covers 6.8 acres.
Who is building it?
The applicant is Sunil Mishra.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Mohbhata, Berla, Bametara, Chhattisgarh.
How big is it?
It has a stated cost of ₹62 lakh and a site of 6.8 acres.
When was it filed?
The application was filed on 15 Jul 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 28 Oct 2026 |
| Application filed | 15 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Sunil Mishra |
| Land area | 6.8 acres (2.7 ha) |
| Project cost | ₹62 lakh |
| Village / locality | Mohbhata |
| Taluk / tehsil | Berla |
| District | Bametara |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-03718 |
In context
74 applications in Bametara since January 2022 are in the same category (Mining): 22 approved, 9 filed or under review, and 43 withdrawn, lapsed or rejected. The approved ones took a median of 13 months from filing to approval. At 6.8 acres, this one is larger than 50% of them.
6 other mining leases have applied within 500 m of this site; together with this one they cover 58 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 15 mining leases have applied within 5 km.
Where it is
Mohbhata, Berla, Bametara, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sunil Kumar Mishra — not approved, 0 m away
- Mining project by M/s Shubham Minerals — environmental approval granted, 150 m away
- Mohbhatha Dolomite Quarry — cleared for impact study, 150 m away
- Gopal Prasad Agrawal, Mohbhatha Dolomite Quarry area 3.89Hec. — lapsed, 200 m away
- Mohbhatta Dolomite Quarry Area 3.89 Hec. — lapsed, 200 m away
- Gopal Prasad Agrawal , Mohbhatha Dolomite Quarry Area 3.89hec. — not approved, 200 m away
- Mohbhatha Dolomite Quarry Area 4.56 — cleared for impact study, 350 m away
- M/s Ganpati Minerals Dolomite Mine — environmental approval granted, 900 m away
More from Sunil Mishra in Bametara
- Kodwa Dolomite Quarry Area 3.00 — under environmental review
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.