What is Ghatola Minor Tank Project?
Ghatola Minor Tank Project is a proposed water and irrigation project in Godhatola, Sahaspur Lohara, Kabeerdham, Chhattisgarh. The site covers 98.2 acres.
Who is building it?
The applicant is Water Resources Department.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Godhatola, Sahaspur Lohara, Kabeerdham, Chhattisgarh.
How big is it?
It has a stated cost of ₹12 crore; a site of 98.2 acres and 83.4 acres (33.7 ha) of forest land.
When was it filed?
The application was filed on 6 Feb 2024.
Project details
| Status | More information requested |
|---|---|
| Status since | 7 Jan 2026 |
| Application filed | 6 Feb 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Water Resources Department |
| Land area | 98.2 acres (39.8 ha) |
| Forest land | 83.4 acres (33.7 ha) |
| Project cost | ₹12 crore |
| Village / locality | Godhatola |
| Taluk / tehsil | Sahaspur Lohara |
| District | Kabeerdham |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-03966 |
In context
6 applications in Kabeerdham since January 2022 are in the same category (Water & irrigation): 1 approved, 4 filed or under review, and 1 withdrawn, lapsed or rejected.
Where it is
Godhatola, Sahaspur Lohara, Kabeerdham, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Godhatola Iron Ore Block — forest land use approved, 9.3 km away
- Jagmadwa Minor Tank — under forest review, 11.2 km away
- Preliminary Exploration (G-3 Stage) for Bauxite, Aluminous Laterite and… — forest land use approved, 11.6 km away
- Shri Narayan Yadav — under environmental review, 15.6 km away
- Mohd. Aslam Meman — lapsed, 15.8 km away
- Mohd. Aslam Meman — cleared for impact study, 15.8 km away
- Rajesh Kumar Singhaniya — environmental approval granted, 16.1 km away
- Rajesh Kumar Singhania — cleared for impact study, 16.1 km away
More from Water Resources Department in Kabeerdham
- Headwork & Cannals of Baroda Khurd Minor Tank Scheme — in-principle approval, conditions pending
- Rampur Barenda Diversion Project for Irrigation of 250 hac Agricultural Land — under forest review
- Barodakhurd Tank Scheme — lapsed
- Jagmadwa Minor Tank — under forest review
5 Water Resources Department, Chhattisgarh projects in Kabeerdham
All 10 Water Resources Department, Chhattisgarh projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.