What is Dhondhra Ordinary Stone Quarry of Vinod Singh Rathore?
Dhondhra Ordinary Stone Quarry of Vinod Singh Rathore is a proposed mining project in Dhondara, Konta, Sukma, Chhattisgarh. The site covers 2.5 acres.
Who is building it?
The applicant is Vinod Singh Rathore.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Dhondara, Konta, Sukma, Chhattisgarh.
How big is it?
It has a stated cost of ₹30 lakh and a site of 2.5 acres.
When was it filed?
The application was filed on 26 Oct 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 18 Nov 2026 |
| Application filed | 26 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Vinod Singh Rathore |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹30 lakh |
| Village / locality | Dhondara |
| Taluk / tehsil | Konta |
| District | Sukma |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-04331 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 26 Oct 2026 (this page) | Under environmental review | 2.5 acres | ₹30 lakh |
| New project filed 11 Sept 2025 | Under environmental review | 2.5 acres | ₹30 lakh |
In context
14 applications in Sukma since January 2022 are in the same category (Mining): 5 approved, 7 filed or under review, and 2 withdrawn, lapsed or rejected. At 2.5 acres, this one is smaller than 79% of them.
No other mining lease on record is within 500 m of this site; 4 have applied within 5 km.
Where it is
Dhondara, Konta, Sukma, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Dhondhra Ordinary Stone Quarry of Vinod Singh Rathore — under environmental review, 0 m away
- Dhodhra Ordinary Stone Quarry (M/s Transsoft Infra) — lapsed, 1.5 km away
- Dhodhra Ordinary Stone Quarry (M/s Transsoft Infra) — environmental approval granted, 1.5 km away
- Dhondra Ordinary Stone Quarry (Temporary Permit), Applicant- Shri Shailendra… — environmental approval granted, 2.3 km away
- Arjun Kumar Rajwade — more information requested, 4.7 km away
- Konta Sand Quarry — under environmental review, 4.8 km away
- BharatNet Project Phase II Sukma Forest Division — lapsed, 48.2 km away
- Golabekur Ordinary Stone Quarry — under environmental review, 55.7 km away
About this information