Environmental approval grantedBuildings & townships · Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu

Mangalam Heights

Mangalam Heights is an approved residential project in Silvassa, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu. The site covers 2.2 acres. Its stated project cost is ₹54.2 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 28 May 2026).

See it on the live map All projects in Dadra & Nagar Haveli

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is Mangalam Heights?

Mangalam Heights is an approved residential project in Silvassa, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu. The site covers 2.2 acres.

Who is building it?

The applicant is Mangalam Developers.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 28 May 2026), as of 27 Nov 2026.

Where is it?

In Silvassa, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu.

How big is it?

It has a stated cost of ₹54.2 crore and a site of 2.2 acres.

When was it filed?

The application was filed on 17 Dec 2025.

Project details

StatusEnvironmental approval granted
Status since28 May 2026
Application filed17 Dec 2025
Approval soughtEnvironmental approval
Application typeExpansion
SectorBuildings & townships
ApplicantMangalam Developers
UseResidential
Land area2.2 acres (0.9 ha)
Project cost₹54.2 crore
Village / localitySilvassa
Taluk / tehsilDadra & Nagar Haveli
DistrictDadra & Nagar Haveli
StateDadra and Nagar Haveli and Daman and Diu
Location fromSite boundary on record
Our referenceWID-DN-00037

What the filings say

What is planned

Mangalam Developers is expanding a residential-cum-commercial project named Mangalam Heights in Silvassa. The applicant's conceptual plan states that the project is being developed on a total land area of 9,000 square metres (0.9 hectares). The expansion involves adding four new buildings (five wings) to the existing two buildings on the site.

The completed project is planned to include:

ItemDetail
Total Plot Area9,000.00 m²
Total Built-up Area42,777.37 m²
Ground Coverage3,450.59 m²
Total Residential Units450
Total Commercial Units34
Maximum Building Height44.10 m (Wing E) / 43.54 m (Wings C, D, F, G)
Total Parking Provided443 PCU

Layout and design

The site layout includes a 1,700 square metre greenbelt area, representing approximately 18.9% of the total land. Internal roads will occupy 1,181 square metres. The project features a basement parking level of 3,573.99 square metres and a stilt parking area of 1,846.85 square metres.

Building Wing E is planned as a basement, stilt, and 14-floor structure with a height of 44.10 metres. Wings A and B are existing structures; Wing A has four floors and Wing B has nine floors. The new construction will use RCC and brick masonry.

Land and surroundings

The project is located at Survey No. 70/3/1/1 in Kamli Faliya, Silvassa. The site is situated within the Silvassa Municipal Council area and falls under Development Zone II. The surrounding terrain is described as undulating.

Environmentally sensitive areas within a 15 km radius include the Dadra and Nagar Haveli (DNH) Wildlife Sanctuary (1.28 km West), the Eco-Sensitive Zone of DNH Wildlife Sanctuary (1.18 km West), and the Damanganga River (1.14 km West-Southwest). The nearest railway station is Bhilad, approximately 12.02 km away.

Water, power and access

During the operational phase, the total water requirement is estimated at 330.85 kilolitres per day (KLD). This includes 200.87 KLD of fresh water, to be supplied by the Silvassa Municipal Council and in-house borewells, and 131.85 KLD of recycled water.

Power will be sourced from Torrent Power with a peak demand of 1.3 MW. A 500 kVA diesel generator set is proposed for emergency backup. Access to the site is provided via an 18-metre wide road on the north side.

Environmental safeguards

The applicant proposes to install a Sewage Treatment Plant (STP) with a capacity of 280 KLD. Treated sewage will be reused for flushing (93.53 KLD) and gardening (6.8 KLD), with the remaining 143.69 KLD discharged into the municipal sewerage pipeline.

Solid waste management includes an Organic Waste Converter (OWC) with a capacity of 800 kg per day to treat organic waste. Non-biodegradable waste (approximately 247.10 kg/day) will be sold to local vendors or collected by the municipal council. For rainwater harvesting, the plan includes three recharge wells and three recharge pits. The project also incorporates 328 solar panels on the terrace with a total capacity of 188,100 Watts.

Mangalam Heights site plan and layout

4 drawings from the project's filings. Sign in free to see them.

Mangalam Heights: Site Layout: building wings, internal roads, and parking areas (preview)🔒 Sign in free to see it
Site Layout: building wings, internal roads, and parking areas
Mangalam Heights: Master Plan: proposed expansion layout and greenbelt (preview)🔒 Sign in free to see it
Master Plan: proposed expansion layout and greenbelt
Mangalam Heights: Basement Floor Plan: parking layout and service areas (preview)🔒 Sign in free to see it
Basement Floor Plan: parking layout and service areas
Mangalam Heights: Location Map: project site within the DNH-PDA development zone (preview)🔒 Sign in free to see it
Location Map: project site within the DNH-PDA development zone

In context

52 applications in Dadra & Nagar Haveli since January 2022 are in the same category (Buildings & townships): 27 approved, 12 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 2.2 acres, this one is smaller than 77% of them.

46 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Silvassa, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.