Diversion of Forest Land for the laying of 11 KV HDD Underground Electric Cable for the Netaji Subhas Chandra Bose Military Academy, Randha is an approved power project in Mota Randha, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu. The site covers 0.1 acres.
Who is building it?
The applicant is Dadra and Nagar Haveli and Daman and Diu Power Distribution Corporation Lim.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 16 Oct 2024), as of 27 Nov 2026.
Where is it?
In Mota Randha, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu.
How big is it?
It has a stated cost of ₹65 lakh; a site of 0.1 acres and 290 m² of forest land.
When was it filed?
The application was filed on 29 Nov 2023.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 16 Oct 2024 |
| Application filed | 29 Nov 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Dadra and Nagar Haveli and Daman and Diu Power Distribution Corporation Lim |
| Land area | 300 m² |
| Forest land | 290 m² |
| Project cost | ₹65 lakh |
| Village / locality | Mota Randha |
| Taluk / tehsil | Dadra & Nagar Haveli |
| District | Dadra & Nagar Haveli |
| State | Dadra and Nagar Haveli and Daman and Diu |
| Location from | Site boundary on record |
| Our reference | WID-DN-00091 |
In context
18 applications in Dadra & Nagar Haveli since January 2022 are in the same category (Power): 7 approved, 2 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 15 months from filing to approval. At 0.1 acres, this one is smaller than 100% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mota Randha, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 765 kV D/c Navsari-Padge Transmission line — under coastal review, 700 m away
- Netaji Subhaschandra Bose Military Academy — lapsed, 850 m away
- Building project by M/s. Shree Narayani Infra — returned to applicant, 4.5 km away
- Dadra Nagar Havelli 4G Sat USO 2 Others — more information requested, 6.7 km away
- Dadra Nagar Havelli 4G Sat USOF 2 — lapsed, 6.7 km away
- The New Industrial Building Construction Projects of Gulnar Plastics Private… — more information requested, 7.5 km away
- Laying of 11KV HDD Underground Electric Cables from Silli Substation to… — lapsed, 7.6 km away
- Diversion of Forest land (PF/RF) for the Laying of 11KV Underground HDD… — forest land use approved, 7.6 km away
More from Dadra and Nagar Haveli and Daman and Diu Power Distribution Corporation Lim in Dadra & Nagar Haveli
- Diversion of Forest Land (PF) for the laying of 11KV Underground Electric… — forest land use approved
- Diversion of Protected Forest Land for the laying of 11KV underground Electric… — lapsed
- Diversion of Protected Forest Land for the Laying of 11KV Underground HDD… — lapsed
- Diversion of Forest Land for the Laying of 11KV Underground HDD Electric Cable… — lapsed
- Diversion of Forest land (PF/RF) for the Laying of 11KV Underground HDD… — forest land use approved
- Laying of 11KV HDD Underground Electric Cables from Silli Substation to… — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.