Proposed Basalt Quarry bearing lease no. 06/Basalt/06 admeasuring area of 0.4Ha Located on Land Bearing Survey No. 52/0 of Village Uguem Of Sanguem Taluka South Goa, Goa is an approved mining project in Uguem, Sanguem, South Goa, Goa. The site covers 1 acre.
Who is building it?
The applicant is Deodita Stone Crushers.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 16 Aug 2023), as of 27 Nov 2026.
Where is it?
In Uguem, Sanguem, South Goa, Goa.
How big is it?
It has a stated cost of ₹10 lakh and a site of 1 acre.
When was it filed?
The application was filed on 16 Aug 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 16 Aug 2023 |
| Application filed | 16 Aug 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Deodita Stone Crushers |
| Land area | 4,000 m² |
| Project cost | ₹10 lakh |
| Village / locality | Uguem |
| Taluk / tehsil | Sanguem |
| District | South Goa |
| State | Goa |
| Location from | Site boundary on record |
| Our reference | WID-GA-00016 |
In context
67 applications in South Goa since January 2022 are in the same category (Mining): 36 approved, 23 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 1 acre, this one is smaller than 100% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 5.5 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 9 mining leases have applied within 5 km.
Where it is
Uguem, Sanguem, South Goa, Goa. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Extension of Validity of Environment Clearance for Basalt Stone Quarry bearing… — environmental approval granted, 400 m away
- Extension of Validity of Environment Clearance for Basalt Stone Quarry bearing… — lapsed, 400 m away
- Extension of validity of Environment Clearance for Basalt Stone Quarry bearing… — environmental approval granted, 450 m away
- Extension of validity of Environment Clearance for Basalt Stone Quarry bearing… — environmental approval granted, 450 m away
- Extension of validity of Environment Clearance for Basalt Stone Quarry bearing… — environmental approval granted, 550 m away
- Extension of Validity of Environment Clearance for Basalt Stone Quarry bearing… — environmental approval granted, 900 m away
- Extension of Validity of Environment Clearance for Basalt Stone Quarry bearing… — lapsed, 900 m away
- Enhancement of Production Capacity of the Existing Basalt Stone Quarry from… — under environmental review, 1000 m away